| 06/23/2026 | Commercial Electrical Standard | APPROVED | |||
| 06/22/2026 | Fire New Construction Standard | NOT REQUIRED | |||
| 06/30/2026 | Bldg Permits - Post Review Express | PENDING ASSIGNMENT | |||
| 06/29/2026 | Commercial Building Standard | REQUIRES RESUBMIT | Please submit your revised documents and provide a letter with a written response letter addressing each of the comments indicating how the Review comments were resolved. Please note the submittal was incomplete and the plan review was conducted using the information presented. The subsequent review could generate more comments after original comments have been addressed. Please contact me if you have any questions about the below comments. I can be reached at email mark.masek@tucsonaz.gov 1. Provide the signed and sealed structural calculations, prepared by an Arizona licensed registrant, used in the design of this project. IBC 107.2.7 2. Please have the Engineer of Record seal sheet C-004. IBC 107.2.1 3. Provide the City of Tucson Special Inspection Certificate(s) with Parts A and B completed with the next submittal. IBC 107.1 SI form link: https://www.tucsonaz.gov/files/sharedassets/public/v/1/city-services/planning-development-services/documents/special_inspection_certificate.pdf Please contact me if you have any questions about the above comments. Mark Masek Plans Examiner – Building Safety Planning and Development Services | City of Tucson main 520.837.4994 email mark.masek@tucsonaz.gov |
||
| 06/23/2026 | Outdoor Lighting Standard | REQUIRES RESUBMIT | Outdoor Lighting Review TC-COM-0626-00819 (555 E GRANT RD TUCSON, AZ 85705) Plan review for the above referenced structure has been completed. This letter reflects comments to be addressed. Provide updated Plans/calculations and a written response Letter to each of the notated items indicating action taken. Resubmitted plans that do not contain a written response Letter addressing each of the notated items indicating action taken, may be delayed until response letter is received. Contact Jeremy Hamblin with any questions: Jeremy.hamblin@tucsonaz.gov Code reference, 2024 International Building Code (IBC), 2023 National Electrical Code (NEC), 2012 Outdoor Lighting Code (OLC). Outdoor Lighting Review: https://www.tucsonaz.gov/files/sharedassets/public/v/1/pdsd/documents/building-code/2012_outdoor_lighting_code_.pdf 1. The replacement, relocation and installation of new lighting fixtures requires compliance with the City of Tucson Outdoor Lighting Code. 2. Provide an outdoor site lighting plan that meets the requirements of OLC 104.2. Show/locate the different light sources on your site plan, both new and existing. Number the light fixtures on your lighting fixture table and use the same number on your site plan. 3. List the Lighting Area per OLC (typically E3) chapter 3 and used in Table 401.1. Specify the compliance option from Table 401.1 that is being used. Total outdoor light output shall not exceed the lumen limits listed in Table 401.1. 4. Show compliance with City of Tucson Outdoor Lighting Code with an approved lighting calculation in accordance with OLC 104.2.1, 401.2. Include all exterior fixtures on the property in the calculations. List shielded and unshielded lights in the calculation. 5. Show unshielded fixtures with a maximum of 3,000 lumens, OLC 401.4. 6. Show lamps with a maximum of 3500K color temperature, OLC 402.1. 7. Provide the manufacturer’s specification sheets for the outdoor lighting fixtures. Include the lumen and color temperature values for each outdoor fixture type. 8. Indicate whether or not a special inspection is required per sec. 104.2.2, and 106.2. https://www.tucsonaz.gov/files/sharedassets/public/v/1/city-services/planning-development-services/documents/special_inspection_certificate_odl.pdf 9. Specify any exceptions used. 10. Provide Curfew lighting controls If applicable Per section 403. |
||
| 06/12/2026 | Site Engineering Standard | REQUIRES RESUBMIT | Permit Activity Number: TC-COM-0626-00819 (1st Review) Project: INSTALL (1) PRE-ASSEMBLED SUPERCHARGER UNITS - (1 TOTAL) SUPERCHARGER CABINETS - (8 TOTAL) SUPERCHARGER POSTS - (1) TESLA SITE CONTROLLER INSTALL (1) SWITCHBOARD ASSEMBLY WITH INTEGRATED TESLA SITE CONTROLLER AND PRIMARY BROADCAST UNIT · INSTALL (1) UTILITY TRANSFORMER, (1) METER, AND OTHER ASSOCIATED UTILITY EQUIPMENT · INSTALL (2) POLE MOUNTED LUMINAIRES · FUTURE (1) SUPERCHARGER CABINETS · FUTURE (8) SUPERCHARGER POSTS Location: 555 E GRANT RD Review Date: 6/12/2026 Reviewer: Marco Contreras – Engineering Associate Reviewer Contact Information: marco.contreras@tucsonaz.gov Plan review for the above referenced structure has been completed. This letter reflects comments to be addressed to ensure final approval from Site Engineering. To help speed up your resubmittal and facilitate shorter review timelines, please include a response letter along with your updated plans and any supporting calculations. In your response letter, address each comment individually and explain what changes were made and where they can be found in the plans. Please do not mark or highlight changes in the drawings at this stage — revision markups are only used after a permit has been issued. Submit your response letter and updated plan set as two separate files. Site Engineering Review Comments: 1. Site Engineering has completed its review of the submitted building plan set and cross-referenced it against the associated Development Package. However, final approval of Commercial Permit TC-COM-0626-00819 cannot be granted until the associated revision to Development Package TD-DEV-0626-00141 has received full approval and been issued. Per UDC §3.3.3.G, building permits for sites requiring a Development Package may not be issued prior to DP approval, as the building plans must be consistent with an approved site plan. Please resubmit for final approval once the Development Package has been approved and issued by all applicable reviewers. |
||
| 06/30/2026 | Site Zoning Standard | REQUIRES RESUBMIT | PDSD TRANSMITTAL FROM: Bobby Parsons Zoning Section Review PROJECT: TC-COM-0626-00819 - TD-DEV-0626-00141 555 E. Grant Rd. Tucson, AZ 85705 Tesla EV Chargers (1st Review) TRANSMITTAL DATE: 6/30/2026 This site is in the C-1 zone (UDC 4.7.20). Comments: Please resubmit revised drawings along with a detailed response letter which states how all Zoning Review Section comments were addressed. 1. Comment: Site Zoning has reviewed the building plans for compliance with the associated Development Package (DP) TD-DEV-0626-00141. While it appears the building plans match the DP, Site zoning cannot approve this permit until the DP is approved by all review agencies. 2. Comment: Additional comments may be forthcoming based on responses to zoning comments and plans submitted. If you have any questions about this transmittal, please contact Bobby Parsons at Robert.Parsons@tucsonaz.gov. |
||
| 06/09/2026 | PDSD Application Completeness Express | REVIEW COMPLETED |