Permit Number: TC-COM-0625-01274
Parcel: 11808009C

Address:
1222 S FREEWAY

Review Status: Requires Resubmit

Review Details: COMMERCIAL REVIEW - FULL v.1

Permit Number - TC-COM-0625-01274
Review Name: COMMERCIAL REVIEW - FULL v.1
Review Status: Requires Resubmit
Review Date Reviewer's Name Type of Review Description Status Comments
07/21/2025 Commercial Building Standard APPROVED Structural(S) Reviewer
Madeline Nelson
mnelson@safebuilt.com
Approved
Reason:
Date Completed : 7/18/2025 11:37:33 PM

Building(B) Reviewer
Andrew Bevis
abevis@safebuilt.com
Approved
Reason:
Date Completed : 7/11/2025 1:31:03 PM
07/14/2025 Outdoor Lighting Standard APPROVED
07/28/2025 Water - PDSD Standard APPROVED
07/28/2025 Bldg Permits - Post Review Express PENDING ASSIGNMENT
07/21/2025 Commercial Electrical Standard REQUIRES RESUBMIT Electrical(E) Reviewer
Ron Ross
rross@safebuilt.com
Denied
Reason:
Date Completed : 7/12/2025 4:55:50 PM
1. Comment: Submitted a duplicate upload of electrical design ie there are two sets of electrical designs uploaded.
2. Need to correct the issue of font type for sheet numbers that show up as boxes, making it impossible to determine
sheet numbers. This also affects other critical areas ie calculations shown on sheet e5.1.
3. e5.1 ELECTRICAL ONE-LINE DIAGRAM AND DETAILS: Font issues for Fault current calculations. It is difficult to
confirm calculations are correct with missing Boxed out information.
07/21/2025 Commercial Mechanical Standard REQUIRES RESUBMIT Mechanical(M) Reviewer
Jorge Valido
jvalido@safebuilt.com
Denied
Reason:
Date Completed : 7/16/2025 11:23:30 AM
1. General - Provide COMcheck Mechanical Compliance Certificate. Any other APPROVED certifying agency is
acceptable. - 2018 IECC Section C403.3.2 HVAC equipment performance requirements.
◦ Shell Review only. (If applicable) Kitchen area will require further Mechanical review and Permitting when
Grease Hood and MAU is installed.
07/21/2025 Commercial Plumbing Standard REQUIRES RESUBMIT Plumbing(P) Reviewer
Perry Hendershott
phendershott@safebuilt.com
Denied
Reason:
Date Completed : 7/20/2025 8:43:42 PM
First Plumbing Review-Shell;
1). General Plbg Plans: Missing Primary & secondary storm piping illustrations & calculations for the roof drains shown on
Arch roof plan. Add Primary & secondary storm piping illustrations & calculations. -2018 IPC 1106.1, 1106.2, 1106.5, 1108
07/25/2025 Site Engineering Standard REQUIRES RESUBMIT TC-COM-0625-01274
1222 S FREEWAY

Site engineering comments are as follows:

1. Please address the differences in the roofed areas from DP20-0269. If these changes are proposed, a revision to the DP will be required. In such case, approval of the building permit will be contingent upon the DP revision’s approval by all reviewers.

Ryan Insalaco – ryan.insalaco@tucsonaz.gov
07/25/2025 Site Zoning Standard REQUIRES RESUBMIT FROM: PDSD Zoning Review Section

PROJECT: TC-COM-0625-01274
1222 S FREEWAY - C-2
Travelers Accommodation, Lodging (1st Review)

TRANSMITTAL DATE: ‎July 25, 2025

COMMENTS: Resubmit revised drawings along with a detailed response letter, which states how all Zoning Review Section comments were addressed.

This site is located in the C-2 zone (UDC 4.7.21). Travelers Accommodation, Lodging is an approved use in the zone (UDC Table 4.8-4).

1. The roofed area shown over the entrance area is not addressed on DP20-0292 and will need to be shown on the DP. Until shown on the DP Zoning cannot approve the building plans.

If you have any questions about this transmittal, please contact Zone1.desk@tucsonaz.gov.
07/23/2025 Fire New Construction Standard REVIEW COMPLETED
07/03/2025 PDSD Application Completeness Express REVIEW COMPLETED