Permit Review Detail
Review Status: Requires Resubmit
Review Details: COMMERCIAL REVIEW - FULL v.2
Permit Number - TC-COM-0625-01162
Review Name: COMMERCIAL REVIEW - FULL v.2
Review Status: Requires Resubmit
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 08/14/2025 | Bldg Permits - Post Review Express | PENDING ASSIGNMENT | |||
| 08/06/2025 | Commercial Building Standard | REQUIRES RESUBMIT | August 6, 2025 2nd Review Shive-Hattery Attn: John Price/Kristen DiBone 4330 N. Campbell Ave. #268 Tucson, Arizona 85718 Re: CGI FEDERAL WAREHOUSE ADDITION City of Tucson Permit Number: TC-COM-0625-01162 Stantec Project Number: 185215066 Stantec File Number: TUC-25-070 Plan review for the above referenced project has been completed. This letter reflects comments to be addressed. PLEASE send all response to comments back to the City through the permit portal! Responses sent directly to Stantec will be ignored. Also, please submit complete copies of all permit documents (i.e. plans, calculations, reports, etc.) even if they have not been changed. Please cloud and delta all changes and provide a letter with a written response to each of the comments indicating the action taken. The scope of this review covers the architectural, structural, plumbing, mechanical, and electrical designs as they relate to the codes adopted by the jurisdiction. All features were checked only to the extent allowed by the submittals provided. All portions of this project are assumed to meet or will meet other departmental requirements, conditions, and concerns before permit approval. Occupancy Group Construction Type Area (Square feet) Occupant Load Automatic Fire Sprinklers Fire Alarms S-1 V-B 4,000 12 Yes Yes Separate Permits: Automatic fire sprinklers and fire alarm. Deferred Submittals: Racking system. Special Inspections: Earthwork, epoxy and expansion anchors, structural steel, masonry, and outdoor lighting. GENERAL COMMENTS 1. Addressed. 2. New Comment: Please ensure with the next submittal all required documents for review are submitted for approval. The latest submittal did not include the project manual. The next submittal should include the following documents: a. Construction documents b. Building thermal envelope comcheck c. Geotechnical report d. Structural calculations e. Mechanical calculations f. Project manual ARCHITECTURAL COMMENTS General 1. Addressed. 2. Previous Comment: Please indicate on the cover that the wood “I” joists and racking system will be provided as part of deferred submittal. Still Required: The deferred submittals listed on the cover sheet includes wood ‘I’ joists and steel stairs. The updated design no longer includes wood ‘I’ joists and there are no steel stairs. Please remove these from the list. 3. Previous Comment: Note on the cover of the drawings that special inspection is required for earthwork, epoxy and expansion anchors, structural steel, masonry, water-resistive barrier coating and outdoor lighting. Also, provide City of Tucson special inspection certificate(s) with Parts A and B completed. Make sure that the owner or their legal representative signs the form. Still Required: A special inspection certificate was not provided for the required special inspections. Please also remove concrete, wood, and water-resistant barrier coating from the special inspection list as these are no longer required with the updated design. Sheet G000.1 1. Addressed. Sheet G100.1 1. Addressed. Sheet A101.1 1. Addressed. 2. Addressed. STRUCTURAL COMMENTS General 1. Addressed. Sheet S1.3.2 1. Addressed. MECHANICAL COMMENTS General 1. Addressed. PLUMBING COMMENTS There are no comments. ELECTRICAL COMMENTS Sheet E601 1. Addressed. 2. Addressed. Should you have any questions regarding the plan review comments, please contact the plan reviewer listed for the appropriate discipline. Plans reviewed by: Trevor Bies, Senior Plan Reviewer 602-338-9922 trevor.bies@stantec.com |
||
| 08/06/2025 | Commercial Electrical Standard | REQUIRES RESUBMIT | August 6, 2025 2nd Review Shive-Hattery Attn: John Price/Kristen DiBone 4330 N. Campbell Ave. #268 Tucson, Arizona 85718 Re: CGI FEDERAL WAREHOUSE ADDITION City of Tucson Permit Number: TC-COM-0625-01162 Stantec Project Number: 185215066 Stantec File Number: TUC-25-070 Plan review for the above referenced project has been completed. This letter reflects comments to be addressed. PLEASE send all response to comments back to the City through the permit portal! Responses sent directly to Stantec will be ignored. Also, please submit complete copies of all permit documents (i.e. plans, calculations, reports, etc.) even if they have not been changed. Please cloud and delta all changes and provide a letter with a written response to each of the comments indicating the action taken. The scope of this review covers the architectural, structural, plumbing, mechanical, and electrical designs as they relate to the codes adopted by the jurisdiction. All features were checked only to the extent allowed by the submittals provided. All portions of this project are assumed to meet or will meet other departmental requirements, conditions, and concerns before permit approval. Occupancy Group Construction Type Area (Square feet) Occupant Load Automatic Fire Sprinklers Fire Alarms S-1 V-B 4,000 12 Yes Yes Separate Permits: Automatic fire sprinklers and fire alarm. Deferred Submittals: Racking system. Special Inspections: Earthwork, epoxy and expansion anchors, structural steel, masonry, and outdoor lighting. GENERAL COMMENTS 1. Addressed. 2. New Comment: Please ensure with the next submittal all required documents for review are submitted for approval. The latest submittal did not include the project manual. The next submittal should include the following documents: a. Construction documents b. Building thermal envelope comcheck c. Geotechnical report d. Structural calculations e. Mechanical calculations f. Project manual ARCHITECTURAL COMMENTS General 1. Addressed. 2. Previous Comment: Please indicate on the cover that the wood “I” joists and racking system will be provided as part of deferred submittal. Still Required: The deferred submittals listed on the cover sheet includes wood ‘I’ joists and steel stairs. The updated design no longer includes wood ‘I’ joists and there are no steel stairs. Please remove these from the list. 3. Previous Comment: Note on the cover of the drawings that special inspection is required for earthwork, epoxy and expansion anchors, structural steel, masonry, water-resistive barrier coating and outdoor lighting. Also, provide City of Tucson special inspection certificate(s) with Parts A and B completed. Make sure that the owner or their legal representative signs the form. Still Required: A special inspection certificate was not provided for the required special inspections. Please also remove concrete, wood, and water-resistant barrier coating from the special inspection list as these are no longer required with the updated design. Sheet G000.1 1. Addressed. Sheet G100.1 1. Addressed. Sheet A101.1 1. Addressed. 2. Addressed. STRUCTURAL COMMENTS General 1. Addressed. Sheet S1.3.2 1. Addressed. MECHANICAL COMMENTS General 1. Addressed. PLUMBING COMMENTS There are no comments. ELECTRICAL COMMENTS Sheet E601 1. Addressed. 2. Addressed. Should you have any questions regarding the plan review comments, please contact the plan reviewer listed for the appropriate discipline. Plans reviewed by: Trevor Bies, Senior Plan Reviewer 602-338-9922 trevor.bies@stantec.com |
||
| 08/06/2025 | Commercial Mechanical Standard | REQUIRES RESUBMIT | August 6, 2025 2nd Review Shive-Hattery Attn: John Price/Kristen DiBone 4330 N. Campbell Ave. #268 Tucson, Arizona 85718 Re: CGI FEDERAL WAREHOUSE ADDITION City of Tucson Permit Number: TC-COM-0625-01162 Stantec Project Number: 185215066 Stantec File Number: TUC-25-070 Plan review for the above referenced project has been completed. This letter reflects comments to be addressed. PLEASE send all response to comments back to the City through the permit portal! Responses sent directly to Stantec will be ignored. Also, please submit complete copies of all permit documents (i.e. plans, calculations, reports, etc.) even if they have not been changed. Please cloud and delta all changes and provide a letter with a written response to each of the comments indicating the action taken. The scope of this review covers the architectural, structural, plumbing, mechanical, and electrical designs as they relate to the codes adopted by the jurisdiction. All features were checked only to the extent allowed by the submittals provided. All portions of this project are assumed to meet or will meet other departmental requirements, conditions, and concerns before permit approval. Occupancy Group Construction Type Area (Square feet) Occupant Load Automatic Fire Sprinklers Fire Alarms S-1 V-B 4,000 12 Yes Yes Separate Permits: Automatic fire sprinklers and fire alarm. Deferred Submittals: Racking system. Special Inspections: Earthwork, epoxy and expansion anchors, structural steel, masonry, and outdoor lighting. GENERAL COMMENTS 1. Addressed. 2. New Comment: Please ensure with the next submittal all required documents for review are submitted for approval. The latest submittal did not include the project manual. The next submittal should include the following documents: a. Construction documents b. Building thermal envelope comcheck c. Geotechnical report d. Structural calculations e. Mechanical calculations f. Project manual ARCHITECTURAL COMMENTS General 1. Addressed. 2. Previous Comment: Please indicate on the cover that the wood “I” joists and racking system will be provided as part of deferred submittal. Still Required: The deferred submittals listed on the cover sheet includes wood ‘I’ joists and steel stairs. The updated design no longer includes wood ‘I’ joists and there are no steel stairs. Please remove these from the list. 3. Previous Comment: Note on the cover of the drawings that special inspection is required for earthwork, epoxy and expansion anchors, structural steel, masonry, water-resistive barrier coating and outdoor lighting. Also, provide City of Tucson special inspection certificate(s) with Parts A and B completed. Make sure that the owner or their legal representative signs the form. Still Required: A special inspection certificate was not provided for the required special inspections. Please also remove concrete, wood, and water-resistant barrier coating from the special inspection list as these are no longer required with the updated design. Sheet G000.1 1. Addressed. Sheet G100.1 1. Addressed. Sheet A101.1 1. Addressed. 2. Addressed. STRUCTURAL COMMENTS General 1. Addressed. Sheet S1.3.2 1. Addressed. MECHANICAL COMMENTS General 1. Addressed. PLUMBING COMMENTS There are no comments. ELECTRICAL COMMENTS Sheet E601 1. Addressed. 2. Addressed. Should you have any questions regarding the plan review comments, please contact the plan reviewer listed for the appropriate discipline. Plans reviewed by: Trevor Bies, Senior Plan Reviewer 602-338-9922 trevor.bies@stantec.com |
||
| 08/06/2025 | Commercial Plumbing Standard | REQUIRES RESUBMIT | August 6, 2025 2nd Review Shive-Hattery Attn: John Price/Kristen DiBone 4330 N. Campbell Ave. #268 Tucson, Arizona 85718 Re: CGI FEDERAL WAREHOUSE ADDITION City of Tucson Permit Number: TC-COM-0625-01162 Stantec Project Number: 185215066 Stantec File Number: TUC-25-070 Plan review for the above referenced project has been completed. This letter reflects comments to be addressed. PLEASE send all response to comments back to the City through the permit portal! Responses sent directly to Stantec will be ignored. Also, please submit complete copies of all permit documents (i.e. plans, calculations, reports, etc.) even if they have not been changed. Please cloud and delta all changes and provide a letter with a written response to each of the comments indicating the action taken. The scope of this review covers the architectural, structural, plumbing, mechanical, and electrical designs as they relate to the codes adopted by the jurisdiction. All features were checked only to the extent allowed by the submittals provided. All portions of this project are assumed to meet or will meet other departmental requirements, conditions, and concerns before permit approval. Occupancy Group Construction Type Area (Square feet) Occupant Load Automatic Fire Sprinklers Fire Alarms S-1 V-B 4,000 12 Yes Yes Separate Permits: Automatic fire sprinklers and fire alarm. Deferred Submittals: Racking system. Special Inspections: Earthwork, epoxy and expansion anchors, structural steel, masonry, and outdoor lighting. GENERAL COMMENTS 1. Addressed. 2. New Comment: Please ensure with the next submittal all required documents for review are submitted for approval. The latest submittal did not include the project manual. The next submittal should include the following documents: a. Construction documents b. Building thermal envelope comcheck c. Geotechnical report d. Structural calculations e. Mechanical calculations f. Project manual ARCHITECTURAL COMMENTS General 1. Addressed. 2. Previous Comment: Please indicate on the cover that the wood “I” joists and racking system will be provided as part of deferred submittal. Still Required: The deferred submittals listed on the cover sheet includes wood ‘I’ joists and steel stairs. The updated design no longer includes wood ‘I’ joists and there are no steel stairs. Please remove these from the list. 3. Previous Comment: Note on the cover of the drawings that special inspection is required for earthwork, epoxy and expansion anchors, structural steel, masonry, water-resistive barrier coating and outdoor lighting. Also, provide City of Tucson special inspection certificate(s) with Parts A and B completed. Make sure that the owner or their legal representative signs the form. Still Required: A special inspection certificate was not provided for the required special inspections. Please also remove concrete, wood, and water-resistant barrier coating from the special inspection list as these are no longer required with the updated design. Sheet G000.1 1. Addressed. Sheet G100.1 1. Addressed. Sheet A101.1 1. Addressed. 2. Addressed. STRUCTURAL COMMENTS General 1. Addressed. Sheet S1.3.2 1. Addressed. MECHANICAL COMMENTS General 1. Addressed. PLUMBING COMMENTS There are no comments. ELECTRICAL COMMENTS Sheet E601 1. Addressed. 2. Addressed. Should you have any questions regarding the plan review comments, please contact the plan reviewer listed for the appropriate discipline. Plans reviewed by: Trevor Bies, Senior Plan Reviewer 602-338-9922 trevor.bies@stantec.com |
||
| 08/14/2025 | Fire New Construction Standard | REQUIRES RESUBMIT | -Make correction to IFC, applicable codes, sheet G100.1. TFD/COT has adopted the 2024 IFC. -Resolve all building comments. Questions: patricia.shelton@tucsonaz.gov |
||
| 07/30/2025 | PDSD Application Completeness Express | REVIEW COMPLETED |