Permit Review Detail
Review Status: Requires Resubmit
Review Details: COMMERCIAL REVIEW - FULL v.2
Permit Number - TC-COM-0623-01477
Review Name: COMMERCIAL REVIEW - FULL v.2
Review Status: Requires Resubmit
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
08/04/2023 | Bldg Permits - Post Review | PENDING ASSIGNMENT | |||
08/04/2023 | Commercial Structural | REQUIRES RESUBMIT | Assuming that you are able to resolve the zoning issues with the Zoning Department, submit your revised drawings along with a detailed response letter, which states how all Building Review Section comments were addressed. 1. We will agree with your proposal of using IBC 406.5 in determining that this parking canopy is an open parking garage using Type I, II or IV construction, that IBC Table 602 exemption C shall not require a fire-resistance rating. 2. However the roof edge is simply the edge of the roof eave, IBC Table 705.2 is to be complied with and projections is to be addressed. 3. You mentioned variance DDO-10-24 reducing the setback to 6 ft on the East property line. In this location, IBC Table 705.2 allowed projection shall apply. You will find that the City of Tucson's Unified Development Code Article 6.4.5.D.1.b will be more stringent where you will be allowed 2 feet of roof overhang into the 6 foot perimeter yard setback. Please correct your drawings to reflect this requirement. 4. Assuming that your request to reduce the setback down to zero at the north property line abutting the property addressed 1020 N TYNDALL AV is approved, IBC Table 705.2 shall apply. The minimum 24 inches from roof edge to property line shall apply. 5. The proposed gutter is too low relative to the top edge of the eave. During heavy rain volume, the water will fly over the gutter outer edge and into the neighboring property. Raise the gutter to address this issue. 6. An Arizona Registrant shall be required to seal/sign/date the Architectural sheets, please comply to this City of Tucson requirement. 7. Detail 101/S002 does not indicate the location vertically of the footing into native soil. Please comply to the building code requirement or Structural Engineer shall specify this requirement. 8. Please respond. |
||
07/13/2023 | Site Engineering | REQUIRES RESUBMIT | See zoning comment | ||
07/06/2023 | Site Zoning | REQUIRES RESUBMIT | ZONING REVIEW TRANSMITTAL FROM: Wyatt Berger Lead Planner PROJECT: TC-COM-0623-01477 901 East 1st Street – R-3 New parking canopy (2nd Review) TRANSMITTAL DATE: July 6, 2023 Please resubmit revised drawings with a detailed response letter stating how all Zoning Review Section comments were addressed. 1. Until active TD-DEV-0623-00292 is approved by all review entities, Zoning cannot approve this specific building permit. If you have any questions about this transmittal, contact me at Wyatt.Berger@tucsonaz.gov or at 520-837-4951. |
||
06/30/2023 | PDSD Application Completeness | REVIEW COMPLETED |