Permit Number: TC-COM-0525-01018
Parcel: 11619131A

Review Status: In Review

Review Details: COMMERCIAL REVIEW - FULL REVISION v.2

Permit Number - TC-COM-0525-01018
Review Name: COMMERCIAL REVIEW - FULL REVISION v.2
Review Status: In Review
Review Date Reviewer's Name Type of Review Description Status Comments
N/A Bldg Permits - Post Review Express PENDING ASSIGNMENT
N/A Commercial Building Standard PENDING ASSIGNMENT
N/A Commercial Electrical Standard PENDING ASSIGNMENT
N/A Commercial Mechanical Standard PENDING ASSIGNMENT
N/A Commercial Plumbing Standard PENDING ASSIGNMENT
07/24/2026 Site Engineering Standard REQUIRES RESUBMIT Permit Activity Number: TC-COM-0525-01018 (1st Review)
Project: New Construction of an auto parts retail store.
Location: 701 W CONGRESS ST
Review Date: 7/24/2026
Reviewer: Marco Contreras – Engineering Associate - Site Engineering
Reviewer Contact: Marco.contreras@tucsonaz.gov
Related cases: TD-DEV-0326-00072

Plan review for the above referenced structure has been completed. This letter reflects comments to be addressed to ensure final approval from Site Engineering.
To help speed up your resubmittal and facilitate shorter review timelines, please include a response letter along with your updated plans and any supporting calculations. In your response letter, address each comment individually and explain what changes were made and where they can be found in the plans. Please do not mark or highlight changes in the drawings at this stage — revision markups are only used after a permit has been issued. Submit your response letter and updated plan set as two separate files.
Site Engineering Review Comments:
1. Site Engineering has completed its review of the submitted building plan set and cross-referenced it against the associated Development Package. However, final approval of Commercial TC-COM-0525-01018 cannot be granted until the associated submission of the revision to Development Package TD-DEV-0325-00069 has received full approval and has been issued. Per UDC §3.3.3.G, building permits for sites requiring a Development Package may not be issued prior to DP approval, as the building plans must be consistent with an approved site plan. Please resubmit for final approval once the Development Package has been approved and issued by all applicable reviewers.
07/30/2026 Site Zoning Standard REQUIRES RESUBMIT Zoning has reviewed the building plans for compliance with the revisions made in development package (DP) TD-DEV-0325-00069; and although the plans appear to be in compliance, until the DP is approved by all review agencies Zoning cannot approve this building permit.

For Site Zoning questions, please contact Krista Hansen at krista.hansen@tucsonaz.gov.
07/08/2026 PDSD Application Completeness Express REVIEW COMPLETED