Permit Number: TC-COM-0525-01005
Parcel: 141019160

Review Status: Requires Resubmit

Review Details: COMMERCIAL REVIEW - FULL v.2

Permit Number - TC-COM-0525-01005
Review Name: COMMERCIAL REVIEW - FULL v.2
Review Status: Requires Resubmit
Review Date Reviewer's Name Type of Review Description Status Comments
07/30/2025 Commercial Plumbing Standard APPROVED Plumbing(P) Reviewer
Perry Hendershott
phendershott@safebuilt.com
Approved
Reason:
Date Completed : 7/29/2025 9:26:50 PM
08/07/2025 Outdoor Lighting Standard APPROVED Approved with the following 'Pre-issuance' condition added:
An Outdoor Lighting Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit. https://www.tucsonaz.gov/files/sharedassets/public/v/1/city-services/planning-development-services/documents/special_inspection_certificate_odl.pdf
08/14/2025 Water - PDSD Standard APPROVED
08/14/2025 Bldg Permits - Post Review Express PENDING ASSIGNMENT
07/30/2025 Commercial Electrical Standard REQUIRES RESUBMIT Electrical(E) Reviewer
Ron Ross
rross@safebuilt.com
Denied
Reason:
Date Completed : 7/25/2025 2:37:16 PM
1. E4.3: Single Line Riser Diagram needs to provide Overcurrent protection for MDP Panel per NEC 240.4. This can be
through the Disconnect switch (enclosed CB or Fused Disc.) or a Main Circuit breaker in the MDP panel. Current
design has no overcurrent protection shown. Not Addressed
◦ Response: Design Complies. Please refer to sheet E4.3 Single Line Riser Diagram showing a disconnect
switch on the SES.
◦ Design needs to comply with NEC 240.4 or NEC 230.71. NEC 240.4 requires overcurrent protection for service
feeder. Current design shows a Non-Fused disconnect which provides no overcurrent protection.
2. E4.3: Need to provide conductor and grnd wire size for Computer panel on Single Line Riser Diagram. Addressed
3. E4.3: PV system needs to be called out as a future permit submittal or provide raceway/feeder information and
equipment values if it is to be permitted with this application. Not Addressed
◦ Response: Sheet E4.3 – Revised PV system to coordinate with solar drawings (under separate permit). Feeder
information for the PV system has been added.
◦ Conductors are undersized for PV CB #7 located in MDP. Reduce size of 80 amp CB or upsized #6 AWG
conductors to PV system for coordinated overcurrent protection.
4. ES1.2: Need to perform a Tucson City Lumens per acre calculation as per local electrical code requirement and show
compliance. Addressed on ES1.3
08/12/2025 Site Engineering Standard REQUIRES RESUBMIT Permit: TC-COM-0525-01005
Location: 5651 S HOUGHTON RD
Review Date: 8/12/2025
Site Engineering Comments:
1. Site Engineering will be unable to review and approve permit TC-COM-0525-01005 until the associated Development package TD-DEV-0525-00132 has been reviewed and approved.

If you have any questions or concerns, please contact
Marco Contreras
Marco.contreras@tucsonaz.gov
08/11/2025 Site Zoning Standard REQUIRES RESUBMIT PDSD TRANSMITTAL

FROM: Ramiro Olivarez
Zoning Review Section

PROJECT: TC-COM-0525-01005
141019160 – PAD-12 Zoning
(2nd Review)

TRANSMITTAL DATE: August 11, 2025

This site is located in PAD-12

COMMENTS: Please resubmit revised drawings and a detailed response letter, which states how all Zoning Review Section comments were addressed.


1. Comment: Final Site Zoning approval of this plan cannot occur until the development package (DP), TD-DEV-0525-00132, is approved by all review agencies. Once approved, please resubmit the building permit corrected construction plans.

2. Comment: The specific use within the building footprint is “Food Service” not “Restaurant”.

3. Comment: Additional comments may be forthcoming on the next review based on the proposed use and applicable use specific standards.

RESUBMITTAL OF THE FOLLOWING IS REQUIRED: As noted above.

If you have any questions about this transmittal, please contact Ramiro Olivarez Ramiro.Olivarez@tucsonaz.gov
07/24/2025 PDSD Application Completeness Express REVIEW COMPLETED