Permit Number: TC-COM-0524-00779
Parcel: 13816001G

Review Status: Requires Resubmit

Review Details: COMMERCIAL REVIEW - FULL v.1

Permit Number - TC-COM-0524-00779
Review Name: COMMERCIAL REVIEW - FULL v.1
Review Status: Requires Resubmit
Review Date Reviewer's Name Type of Review Description Status Comments
06/10/2024 Water - PDSD APPROVED
06/10/2024 Bldg Permits - Post Review Express PENDING ASSIGNMENT
05/23/2024 External Reviewers - SAFEBuilt REQUIRES RESUBMIT Structural(S) Reviewer
Madeline Nelson
mnelson@safebuilt.com
Denied
Reason:
Date Completed : 5/22/2024 6:40:36 PM
1. UPDATES: For project updates, please submit sheets with all changes clearly marked in revision clouds. Please provide a written response to each comment; updates without a clear response to all comments may not be reviewed. If you have any questions regarding the comments, you may contact me directly. Updates may result in additional comments.

2. GEOTECHNICAL REPORT: Please provide a copy of the site-specific geotechnical report for this project referenced in the structural general notes. The report should support the appropriateness of the selected foundation system for the project site. All building code references must be updated to the current code adopted by the City. [Please note that the allowable soil bearing pressure used by Specialty Engineer, Jimco Sales & Manufacturing, does not match the structural general notes on Sheet S0.1 (Refer to Dwg No CA5). Maximum allowable bearing pressure will need to be confirmed in the geotechnical report and may require revisions by Jimco.]



Building(B) Reviewer
Janet Matz
jmatz@safebuilt.com
Denied
Reason:
Date Completed : 5/11/2024 1:20:30 AM
Sheet G1.0
1. Update the sheet index so it matches the drawings that were provided in the set.

2. Include to the list of applicable codes the City of Tucson/ Pima County Outdoor Lighting Code.
◦ Site plan

3. Indicate the accessible route from the new diesel pumps to the interior of the convenience center where the new “Diesel Smart Desk” will be located. It appears that there may be an existing sidewalk on the south side of the store, but it does not appear to be connected to the new driveway. 2009 ICC A117.1 chapter 402.1.



Mechanical(M) Reviewer
Jorge Valido
jvalido@safebuilt.com
Denied
Reason:
Date Completed : 5/20/2024 2:34:42 PM
1. General - If applicable provide Mechanical plans for existing building. Show all new and existing duct work. Show all new and existing A/C equipment. Show new refrigeration, If no Mechanical work is to be performed, respond with "NO Mechanical work in the scope for this job" - 2018 IBC Section [A]107.2.1Information on construction documents. - 2018 IECC Section C103.2Information on construction documents.



Electrical(E) Reviewer
Ron Ross
rross@safebuilt.com
Denied
Reason:
Date Completed : 5/11/2024 7:40:23 PM
1. E1.3 ELECTRICAL SITE DETAILS: Sheet is missing from set. Need to provide or confirm that it is no longer needed.

2. Comment concerning sheet E2.0 ELECTRICAL FLOOR PLAN: Keynote 8 is used, but no description provided.

3. Comment concerning sheet E2.1 ELECTRICAL FLOOR PLAN: Sheet is not shown on sheet legend.

4. Comment concerning sheet E7.1 PANEL SCHEDULES: New Panelboard (NEW) schedule is not identified/named, nor is it shown/located on drawings to show compliance with NEC 110.26.

5. Comment concerning sheet SE1.0 Keynotes are poorly aligned and could not locate Keynotes 1 and 9.



Plumbing(P) Reviewer
Perry Hendershott
phendershott@safebuilt.com
Denied
Reason:
Date Completed : 5/21/2024 9:39:34 PM
First Plumbing Review:
1). Plan sheets Tk101 & Tk506: each water hydrant needs its own shut off valve & vacuum breaker. Add an individual shut off valve & vacuum breaker at each water hydrant. -2018 IPC 606.2 & 608.16.4.2
06/04/2024 Site Engineering REQUIRES RESUBMIT See zoning comment
06/03/2024 Site Zoning REQUIRES RESUBMIT FROM: PDSD Zoning Review Section

PROJECT: TC-COM-0524-00779 - TD-DEV-0324-00089
530 E VALENCIA RD - C-2
Multifamily (1st Review)

TRANSMITTAL DATE:‎June 3, 2024

COMMENTS: Resubmit revised drawings along with a detailed response letter, which states how all Zoning Review Section comments were addressed.

This site is located in the C-2 zone (UDC 4.7.21). General Merchandise Sales, excluding Large Retail Establishment, is a permitted use in the zone (UDC Table 4.8-4), subject to Use Specific Standard 4.9.9.B.1.

1. COMMENT: Zoning has reviewed the building plan for compliance with TD-DEV-0324-00089 and although the plans appear to match the DP, Zoning cannot approve the building plans until the DP is approved by all review agencies.

If you have any questions about this transmittal, please contact Zone1.desk@tucsonaz.gov.
05/26/2024 Fire New Construction REVIEW COMPLETED -All fuel related equipment requires a separate permit from TFD. Contact Inspector Silva for submittal and inspection information, 520-419-9177
jesus.silva@tucsonaz.gov
5208377094
05/08/2024 PDSD Application Completeness Express REVIEW COMPLETED