Permit Review Detail
Review Status: Requires Resubmit
Review Details: COMMERCIAL REVIEW - FULL REVISION v.1
Permit Number - TC-COM-0426-00572
Review Name: COMMERCIAL REVIEW - FULL REVISION v.1
Review Status: Requires Resubmit
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 07/08/2026 | Commercial Building Standard | APPROVED | |||
| 07/07/2026 | Water - PDSD Standard | APPROVED | |||
| 06/18/2026 | Site Engineering Standard | NOT REQUIRED | |||
| 06/17/2026 | Site Zoning Standard | NOT REQUIRED | |||
| 07/08/2026 | Bldg Permits - Post Review Express | PENDING ASSIGNMENT | |||
| 06/25/2026 | Commercial Electrical Standard | REQUIRES RESUBMIT | Commercial Electrical Review TC-COM-0426-00572 (3025 E SPEEDWAY BL TUCSON, AZ 85716) Plan review for the above referenced structure has been completed. This letter reflects comments to be addressed. Provide updated Plans/calculations and a written response Letter to each of the notated items indicating action taken. Resubmitted plans that do not contain a written response Letter addressing each of the notated items indicating action taken, may be delayed until response letter is received. Code reference, 2024 International Building Code (IBC), 2023 National Electrical Code (NEC), 2012 Outdoor Lighting Code (OLC). https://www.tucsonaz.gov/files/sharedassets/public/v/1/pdsd/documents/building-code/2012_outdoor_lighting_code_.pdf Contact Jeremy Hamblin with any questions: Jeremy.hamblin@tucsonaz.gov 1. Show all new receptacles with GFCI protection, per NEC 210.8(B)(3). May require GFCI breakers if receptacle GFCI devices are not readily accessible. 2. Note or show all conduits passing into or out-of the walk-in fridge unit, with sealant and expansion joints per NEC 300.7(A) & (B). |
||
| 07/07/2026 | Commercial Mechanical Standard | REQUIRES RESUBMIT | 1. Show that the walk-in cooler and the walk-in freezer meet the efficiency requirements of Tables C403.12.2.1(2) and Table C403.12.2.1(3), IECC 2024. Reference: Section C403.12, IECC 2024. 2. The design of the proposed walk-in cooler rejects the heat of refrigeration to the interior of the suite. Verify that the capacity of the installed HVAC equipment is capable of handling this additional load. Reference: Section 312.1, IMC 2024. If you have any questions about this review comment, I can be reached at Robert.Sherry@tucsonaz.gov. Note: Activity TC-COM-0224-00376 has no relation to TC-COM-0426-00572. |
||
| 07/07/2026 | Commercial Plumbing Standard | REQUIRES RESUBMIT | Indirect waste piping that has a developed length greater than 30-inches (30”) when measured horizontally or greater than 54-inches (54”) in total developed length shall be trapped. Exception: indirect waste piping conveying only clear-water waste (e.g. effluent from a sanitizing compartment) does not require a trap. Provide a detail of the installation of the relocated dump sink, showing the trapped waste line and the installation of the air admittance valve. Reference: Section 802.3, IPC 2024. If you have any questions about this review comment, I can be reached at Robert.Sherry@tucsonaz.gov |
||
| 06/21/2026 | Fire New Construction Standard | REVIEW COMPLETED | |||
| 06/16/2026 | PDSD Application Completeness Express | REVIEW COMPLETED |