Permit Number: TC-COM-0424-00665
Parcel: 13801001D

Address:
6100 S 12TH AV

Review Status: Requires Resubmit

Review Details: COMMERCIAL REVIEW - FULL v.1

Permit Number - TC-COM-0424-00665
Review Name: COMMERCIAL REVIEW - FULL v.1
Review Status: Requires Resubmit
Review Date Reviewer's Name Type of Review Description Status Comments
05/06/2024 Commercial Structural APPROVED
04/24/2024 Site Engineering APPROVED
04/30/2024 Site Zoning APPROVED
04/30/2024 Water - PDSD APPROVED
05/06/2024 Bldg Permits - Post Review Express PENDING ASSIGNMENT
04/30/2024 Commercial Electrical REQUIRES RESUBMIT Please address the electrical plan review comments and provide a written response.

Provide evidence on the plans that the proposed exterior lighting fully complies with the Outdoor Lighting Code. See section 104 for plan submittal requirements.

1. Provide site lighting plans with the following information on the plans;

(a) Provide a complete luminaire schedule.

(b) Full compliance with sections 104.2.1(1), (2), (3).

2 See table 401.1, Include PARCEL SIZE, LIGHTING AREA and OPTION utilized per table 401.1, and indicate this information in the lighting site plan.

3 402.1 (light source color temperature requirements), shielding requirements, etc .

4 Provide calcs for total lumens allowed and total lumens proposed per acre for Full Cut Off and Unshielded per table 401.1. Must include existing to remain lighting.

5 Indicate whether or not a special inspection is required per sec. 104.2.2, and 106.2.

6 Specify any exceptions used.

7 Provide Curfew lighting controls If applicable Per section 403.

8 Provide complete compliance with the 2018 IECC for the interior and exterior lighting where applicable.

Do not confuse the Outdoor Lighting Code with the IECC.

9 Provide complete Pool and Splashpad Equipment Grounding details and electrical wiring methods. If by others or separate permit, indicate this with a note on the electric pool plans.

Ref; 2017 NEC, 2012 Tucson/Pima County Outdoor Lighting Code (OLC), 2018 IBC sec 107.2.1. 2018 IECC.
04/30/2024 Commercial Mechanical REQUIRES RESUBMIT 1. Secure the refrigerant circuit access ports of the condensing units to prevent unauthorized access. Reference: Section 1101.10, IMC 2018.
2. Demonstrate energy code compliance for the building envelope using calculations based on the current code. Reference: Sections C101.5, C103.2, C303, and C401.2, International Energy Conservation Code 2018.
3. Show how one of the “Additional Efficiency Package Options” (C406, IECC 2018) is to be accomplished. Reference: Section C401.2, IECC 2018.
4. Provide heating and cooling load calculations to justify the heating/cooling capacities of FC-1/HPCU-1. Reference: Section C403.1.1 and C403.3.1, IECC 2018.
04/30/2024 Commercial Plumbing REQUIRES RESUBMIT 1. The plumbing floor plans (P1.1), the CW & HW Riser (2/P2.2), and the Plumbing Fixture Schedule (P2.1) show two water closets (P1 and P2) and two urinals (P3 and P4) in the men’s restroom but the Soil & Vent Riser (1/P2.2) shows one water closet (P2) and three urinals (P4, P4 and P3). Coordinate the fixture counts. Reference: Section 107.2.1, IBC 2018.
2. The building sewer serving the two Aquatics Facility Buildings is labeled as 6” on the civil plans and 4” on the plumbing plans. In addition, on the civil plans, the building sewer runs north from the south Aquatics Facility Building and then to the west to connect to the public sewer while the plumbing plan shows the building sewer running south from the north Aquatics Facility building before turning west to connect to the public sewer. Coordinate the plumbing and civil designs. Reference: Section 107.2.1, IBC 2018.
3. Provide cleanouts at the junctions of the building drains and the building sewer. Reference: Section 708.1.3, IPC 2018.
4. An approved 2-way cleanout fitting is allowed to be used at the junction of a building drain and a building sewer; otherwise, cleanouts shall open to allow cleaning only in the direction of flow (see “TWO-WAY CO #6”, UT01 and P1.1). Reference: Section 708.1.8, IPC 2018.
5. The maximum distance between cleanouts shall be 100-feet, measured along the developed pipe length from the upstream entrance of the cleanout. Reference: Section 708.1.1, IPC 2018.
6. The Equipment Room shows floor drains, emergency shower/eyewash, and water supply requirements “PER MEP” but no drawings depict any water supply or a building sewer to the building. How will this building be included in this activity?
04/22/2024 Fire New Construction REQUIRES RESUBMIT -Specify the type of lockset with part number (panic hardware) on the exit gates. Include gate G104. There should be a door schedule included.
-Include pool deck in the safety floor plan, Sheet A1.1, with exiting from pool deck. Show all required exits, with exiting travel distance to a public way.
john.vincent@tucsonaz.gov
5203495581
04/17/2024 PDSD Application Completeness Express REVIEW COMPLETED