Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Number: TC-COM-0324-00549
Parcel: 13809002E

Address:
5951 S 12TH AV

Review Status: Requires Resubmit

Review Details: COMMERCIAL REVIEW - FULL v.2

Permit Number - TC-COM-0324-00549
Review Name: COMMERCIAL REVIEW - FULL v.2
Review Status: Requires Resubmit
Review Date Reviewer's Name Type of Review Description Status Comments
04/23/2024 Site Engineering APPROVED
04/29/2024 Site Zoning APPROVED
04/23/2024 Water - PDSD APPROVED
04/29/2024 Bldg Permits - Post Review PENDING ASSIGNMENT
04/09/2024 External Reviewers - SAFEBuilt REQUIRES RESUBMIT Structural(S) Reviewer
Keith Miller
kmiller@safebuilt.com
Denied
Reason:
Date Completed : 4/8/2024 7:00:54 PM
1. Sheet G: Include a list of special inspections detailed in 2018 IBC Chapter 17.
2. Sheet S5: Include the RTU curb details. (2018 IBC section 107)



Building(B) Reviewer
Keith Miller
kmiller@safebuilt.com
Denied
Reason:
Date Completed : 4/8/2024 6:58:51 PM
1. Sheet G: Specify if the building is sprinklered or has fire alarms. Include lists of deferred submittals and special inspections. (2018 IBC section 107, Chapter 17)
2. Sheet G: Include the ages of the students in a brief description of the use and scope of work fo the building. (2018 IBC section 107)
3. Sheets C2, A1: Show the accessible maneuvering clearances, details, and routes to the classrooms, toilet rooms, and drinking fountains and where they are located. (2018 IBC sections 1104, 1109.2, 1109.5, 2009 ICC A117.1 sections 401, 402, 403, 404)
4. Sheet A5: Show the height of the parapet. (2018 IBC section 107)
5. Sheet S5: Include the RTU curb framing details. (2018 IBC section 107)




Mechanical(M) Reviewer
Keith Miller
kmiller@safebuilt.com
Denied
Reason:
Date Completed : 4/8/2024 7:00:05 PM
1. Sheets A5, M1: Show the fall protection of rooftop equipment less than 10ft to the roof edge meeting the requirements of the 2018 IBC sections 1015.3, 1015.6.
2. Sheet M1: Include the condensate details and disposal. (2018 IMC section 307)



Electrical(E) Reviewer
Keith Miller
kmiller@safebuilt.com
Denied
Reason:
Date Completed : 4/8/2024 6:59:30 PM
1. Sheet E1: Include the lighting calculations and details showing compliance with the 2018 IECC section C405.
2. Sheet E1: Show the RTU disconnect and the GFCI protection of the RTU service receptacle. (2017 NEC sections 422.30, 210.8)
3. Sheet E1: Include the tamper resistant receptacle details meeting the requirements of the 2017 NEC section 406.12.
4. Sheet E2: Correct and coordinate the voltages shown on the new and existing equipment in the one-line diagram, calculations, and panel schedules. Both 120/208v and 120/240v are shown. Include ethe panel schedule of the panel
(not labeled) feeding the new subpanel C. (2018 IBC section 107)
5. Sheet E2: Missing an equipment ground ran with the feeders from the existing to the new panel and a grounding electrode for the separate structure. Include the over current protection device protecting the new panel. (2017 NEC section 225.30, 225.31, 225.32, 250.32)



Plumbing(P) Reviewer
Keith Miller
kmiller@safebuilt.com
Denied
Reason:
Date Completed : 4/8/2024 7:00:28 PM
1. Sheet G: Include the minimum number of plumbing fixture calculations based on the total occupant load determined by the factors listed in the 2018 IBC Table 1004.5 of the existing and new areas. (2018 IPC section 403)
2. Sheet A2: Missing the secondary scuppers for the roof drainage. (2018 IPC section1108)
04/08/2024 Fire New Construction REQUIRES RESUBMIT -Indicate that a fire alarm will be installed per IFC 907.2.3 and is a deferred submittal.
john.vincent@tucsonaz.gov
5203495581
03/28/2024 PDSD Application Completeness REVIEW COMPLETED