Permit Number: TC-COM-0324-00396
Parcel: 121136340

Review Status: Requires Resubmit

Review Details: BUILDING DEFERRED SUBMITTAL REVIEW v.1

Permit Number - TC-COM-0324-00396
Review Name: BUILDING DEFERRED SUBMITTAL REVIEW v.1
Review Status: Requires Resubmit
Review Date Reviewer's Name Type of Review Description Status Comments
12/09/2024 Bldg Permits - Post Review Express PENDING ASSIGNMENT
12/09/2024 Air Balancing/Commissioning Report (Deferred Submittal) Express REQUIRES RESUBMIT 1. The air balance report shows that AC-1, AC-2, AC-3, and AC-4 are not able to achieve their design supply airflow rates. The engineer of record shall review the situation and determine the course of action prior to the air balance report being resubmitted. Reference: Section 403.3.1.5, IMC 2018.
2. The air balance report shows that EF-1 in room 104 (Shower) is not functioning. Repair or replace the exhaust fan in order to achieve the minimum exhaust flow rate required by Table 403.3.1.1, IMC 2018. Correct the deficiency and resubmit the report. Reference: Sections 403.3.1.2 and 403.3.1.5, IMC 2018.
12/09/2024 Water Sterilization Report (Deferred Submittal) Express REQUIRES RESUBMIT The required water disinfection report is incomplete. Your report should contain the results of a bacteriological examination by a licensed testing laboratory of the water in the distribution system after the chlorine has been purged from the system. Section 610.1 of the 2018 International Plumbing Code describes the testing requirements.
12/06/2024 PDSD Application Completeness Express REVIEW COMPLETED