Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit Review Detail
Review Status: Requires Resubmit
Review Details: COMMERCIAL REVIEW - FULL v.1
Permit Number - TC-COM-0323-00868
Review Name: COMMERCIAL REVIEW - FULL v.1
Review Status: Requires Resubmit
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
08/16/2023 | Bldg Permits - Post Review | PENDING ASSIGNMENT | |||
08/08/2023 | External Reviewers - SAFEBuilt | REQUIRES RESUBMIT | Structural(S) Reviewer Daljit Benipal dbenipal@safebuilt.com Conditionally Approved Reason: Date Completed : 8/7/2023 9:24:29 AM 1. The Geotechnical Report for the proposed building per International Building Code 2018, Section 1803.1 was requested, not provided. The Inspector to verify info used on the project from Geotechnical Report. 2. NOTE: Every effort has been made to identify the code violations. Any oversight by the review team shall not be considered an authority to violate, set aside, cancel or alter applicable codes or ordinances. The plan review and permit issuance shall not be considered a warranty or guarantee. The Structural Engineer is responsible for following ALL applicable Federal, State and local Municipal Codes and Ordinances. Building(B) Reviewer Janet Matz jmatz@safebuilt.com Denied Reason: Date Completed : 7/30/2023 12:50:08 AM 1. Previous Comment: Clarify why the architects stamp indicates the documents were signed by Sandy Epstein when the stamp indicates the registered Architect is Isaac Sanford Epstein. Is Sandy a common name or nick name for this registered professional? Please sign the drawings with the legal name of the professional as it appears on their license. The response letter indicates that the drawings were "signed again as the name appears on the stamp" however the drawings that were summited still bear the name Sandy. Update the drawings. Mechanical(M) Reviewer Neil Samaan nsamaan@safebuilt.com Conditionally Approved Reason: Date Completed : 7/26/2023 7:15:05 PM All corrections complied Approved/subject to field approval Electrical(E) Reviewer Ron Ross rross@safebuilt.com Approved Reason: Date Completed : 7/25/2023 3:22:18 PM Plumbing(P) Reviewer Perry Hendershott phendershott@safebuilt.com Denied Reason: Date Completed : 7/30/2023 9:41:59 AM Second Plumbing Review: 1). SAME-Add gutter & down spout sizes with calculations to plan page -A1.3 -IPC 1106.3., 1106.6 2). SAME-Provide Civil site utility piping plan for continuation of of sewer & water as shown on plan pages P2.1 & P1.1 -IPC 106.3.1 3). SAME-Oil interceptor on plan page P1.1 needs to be vented - IPC 1003.9 4). OK 5). OK 6). OK 7). OK 8). OK |
||
07/28/2023 | Site Engineering | REQUIRES RESUBMIT | See zoning comment | ||
07/26/2023 | Site Zoning | REQUIRES RESUBMIT | FROM: PDSD Zoning Review Section PROJECT: TC-COM-0323-00868 5570 E Travel Plaza Wy. Proposed Rezoning to C-3 Trade Service and Repair - Major TRANSMITTAL DATE: ‎April 20, 2023 COMMENTS: Please resubmit revised drawings along with a detailed response letter, which states how all Zoning Review Section comments were addressed. 1. COMMENT: Zoning has reviewed the building plans for compliance with Development Package (DP) TD-DEV-0523-00245 and although the plans appear to be in compliance until the DP is approved by all review agencies Zoning cannot approve the building plans. If you have any questions about this transmittal, please contact Nicholas Martell at Nicholas.Martell@tucsonaz.gov. |
||
08/16/2023 | Fire New Construction | REVIEW COMPLETED | |||
07/24/2023 | PDSD Application Completeness | REVIEW COMPLETED | The applicant will submit a withdrawal for the T21CM09821 permit. |