Permit Review Detail
Review Status: Requires Resubmit
Review Details: COMMERCIAL REVIEW - FULL REVISION v.1
Permit Number - TC-COM-0226-00147
Review Name: COMMERCIAL REVIEW - FULL REVISION v.1
Review Status: Requires Resubmit
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 07/12/2026 | Commercial Building Standard | APPROVED | |||
| 07/10/2026 | Outdoor Lighting Standard | NOT REQUIRED | No modifications to the outdoor lighting. | ||
| 06/26/2026 | Site Engineering Standard | NOT REQUIRED | |||
| 06/25/2026 | Site Zoning Standard | NOT REQUIRED | |||
| 07/14/2026 | Bldg Permits - Post Review Express | PENDING ASSIGNMENT | |||
| 07/10/2026 | Commercial Electrical Standard | REQUIRES RESUBMIT | Commercial electrical Review TC-COM-0226-00147 (5015 S 12TH AV TUCSON, AZ 85706) Plan review for the above referenced structure has been completed. This letter reflects comments to be addressed. Provide updated Plans/calculations and a written response Letter to each of the notated items indicating action taken. Resubmitted plans that do not contain a written response Letter addressing each of the notated items indicating action taken, may be delayed until response letter is received. Code reference, 2024 International Building Code (IBC), 2023 National Electrical Code (NEC), 2012 Outdoor Lighting Code (OLC). https://www.tucsonaz.gov/files/sharedassets/public/v/1/pdsd/documents/building-code/2012_outdoor_lighting_code_.pdf Contact Jeremy Hamblin with any questions: Jeremy.hamblin@tucsonaz.gov 1. This is a commercial project, requiring all documents to be prepared, sealed, signed, and dated by a registered design professional. Provide complete electrical plans, design, and calculations, sealed by an Arizona Registrant. Reference: Arizona Revised Statutes 32-125, Board of Technical Registration Rules R4-30-304, 2018 IBC section 107.1, 2017 NEC, City of Tucson Commercial Plan Submittal Requirements. https://www.tucsonaz.gov/files/sharedassets/public/v/1/pdsd/documents/checklists/commercial_submittal_requirements_july2023.pdf 2. Provide GFCI protection for all new kitchen receptacles, see panel schedule ‘A’, circuits 2 and 4. NEC 210.8(B) & (D). |
||
| 07/13/2026 | Commercial Mechanical Standard | REQUIRES RESUBMIT | 1. Provide a grease drain and collection reservoir for the vertical discharge fan (note: show how rain will be prevented from causing an overflow of the grease collection reservoir.). Reference: Section 506.5.3, IMC 2024. 2. Provide structural calculations and details to show that the Type I hood is supported from the building structure in accordance with Section 507.2.4, IMC 2024 (the hood hanging weight plus the weight of personnel working in or on the hood). Reference: Section 302.1, IMC 2024. 3. Show that the hood installation complies with Section 507.2.6, IMC 2024 with regard to a smooth, cleanable, non-absorbent, and non-combustible material attached to a non-combustible structure (note that wood studs covered by gypsum board and a sheet of stainless steel are considered combustible construction by the IMC) and extending 18” beyond the hood. 4. Clarify the add/alt for the use of a field –fabricated grease duct in lieu of a factory-built grease duct (key note 4.2/M1.01). The practice of using grease duct enclosure material (i.e. fire wrap blanket) to provide clearance to combustibles where a hood penetrates a ceiling is specifically prohibited by Section 507.2.7, IMC 2024 because the grease duct enclosure material has not been listed for this use. See Section 506.3.11.2, IMC 2024 for the hood enclosure requirements. 5. Show how the temperature of the kitchen space is maintained if the make-up air system is not conditioned. Reference: Section 508.1.1, IMC 2024. If you have any questions about this review comment, I can be reached at Robert.Sherry@tucsonaz.gov. |
||
| 07/14/2026 | Commercial Plumbing Standard | REQUIRES RESUBMIT | 1. Clarify the description of WC-1. It is described as a “pressure assisted 1.6 GPF tank-type” water closet, but the model given is not pressure assisted. Reference: Section 107.2.1, IBC 2024. 2. Verify the required minimum gas service pressure for the proposed fryer. Southwest Gas, the local gas utility, provides natural gas at 7” WG, 2 PSIG, and 5 PSIG. Appliances needing gas service at 7” WG or greater will require a gas meter that delivers at least 2 PSIG gas into a regulator located after the meter set. Reference: Section 402.1, IFGC 2024. 3. Clarify the waste connections for the existing hand sink, prep sink, and the ice machine. Show how they relate to the proposed revisions to the building drain. Reference: Section 301.3, IPC 2024. 4. Provide a detail of the thermal expansion tank installation. Reference: Sections 503.1, 606.1, and 607.3, IPC 2024. 5. Verify that the distance from the hot water source to the hot water termination for the public lavatories complies with the requirements of Section C404.5.1, IECC 2024. 6. Provide a cleanout at the junction of the building drain serving the restroom and the new building sewer. Reference: Section 708.1.3, IPC 2024. If you have any questions about this review comment, I can be reached at Robert.Sherry@tucsonaz.gov. |
||
| 07/14/2026 | Water - PDSD Standard | REQUIRES RESUBMIT | Provide the size of the water meter serving this building, the size of the backflow preventer associated with the water meter, and the total water demand served by the water meter (i.e., including the residence located on the property). Note: Tucson Water limits a 5/8” meter to a maximum demand of 20 GPM. Reference: Section 107.2.1, IBC 2024. If you have any questions about this review comment, I can be reached at Robert.Sherry@tucsonaz.gov. |
||
| 07/13/2026 | Fire New Construction Standard | REVIEW COMPLETED | |||
| 06/22/2026 | PDSD Application Completeness Express | REVIEW COMPLETED |