Permit Review Detail
Review Status: Requires Resubmit
Review Details: COMMERCIAL REVIEW - FULL v.1
Permit Number - TC-COM-0223-00715
Review Name: COMMERCIAL REVIEW - FULL v.1
Review Status: Requires Resubmit
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
04/11/2023 | Commercial Mechanical | APPROVED | |||
04/19/2023 | Commercial Structural | APPROVED | |||
04/19/2023 | Bldg Permits - Post Review Express | PENDING ASSIGNMENT | |||
04/06/2023 | Commercial Electrical | REQUIRES RESUBMIT | Please address the electrical plan review comments and provide a written response. Ref; Plan sheet E0.0. Notes located at the bottom right next to the EDA logo, referencing the CNG-E SHEETS. The CNG-E Plans are not found in the plan set. Please re-submit the plan set and include all plan sheets. Ref; 2018 IBC section 107.2.1, 2017 NEC, 2018 IECC. |
||
04/11/2023 | Commercial Energy | REQUIRES RESUBMIT | 1. Demonstrate energy code compliance for the building envelope using calculations based on the current code. Reference: Sections C101.5, C103.2, C303, and C401.2, International Energy Conservation Code 2018. 2. Clarify the difference between wall type E1 and wall type E2. On the floor plan, 1/A2.0, both wall types are shown as being furred-out but the description of wall type E2 depicts a wall that is not furred-out. Reference: Section 107.2.1, IBC 2018. |
||
04/11/2023 | Commercial Plumbing | REQUIRES RESUBMIT | 1. The plumbing general notes call for coordination of the location of the water meter and the backflow preventer with the civil site drawings. Revise the civil site drawings to show the location of the water meter and backflow preventer. Reference: Section 107.2.1, IBC 2018. 2. Revise the civil site drawings to show the location of the existing 8” sewer. Reference: Section 107.2.1, IBC 2018. 3. Specify the piping materials to be employed in this activity. Reference: Section 107.2.1, IBC 2018. 4. The use of saddle-type fittings to connect to a private sewer is prohibited, use directional wye fittings to connect the building sewers to the sewer main. Reference: Section 707.1 (6), IPC 2018 and Detail RWRD 401. 5. Show the vent for the floor sink, P-1, extending through the roof. Reference: Section 901.2.1 and 918.7, IPC 2018. 6. Provide a cleanout at the junction of the building drain and the building sewer. Reference: Section 708.1.3, IPC 2018. 7. Provide secondary (overflow) roof drainage. Reference: Sections 1108.1, 1108.2 and 1108.3, IPC 2018. |
||
03/29/2023 | Site Engineering | REQUIRES RESUBMIT | See zoning comment | ||
03/24/2023 | Site Zoning | REQUIRES RESUBMIT | ZONING REVIEW TRANSMITTAL FROM: PDSD Zoning Review PROJECT: TC-COM-0223-00715 3920 N Sun Tran Bl. – I-1 (1st Review) Transportation Service: Land Carrier TRANSMITTAL: March 24, 2023 This site is located in I-1 zone (UDC 4.7.29). Transportation Service: Land Carrier is a permitted use in the zone, (Table 4.8-5), subject to Use Specific Standards 4.9.13.Q. 1. Per UDC Article 3.3.3.G.2.c A site plan (Development Package) is required for the following types of development: Existing development undergoing a change of use, building structure additions, and/or a reconfiguration of an area outside a building. A development package (DP) meeting the requirements of Administrative Manual (AM) 2-06 must be submitted and approved prior to approval of this building plan. If you have any questions about this transmittal, please contact Zone1.desk@tucsonaz.gov. |
||
04/05/2023 | Fire New Construction | REVIEW COMPLETED | |||
03/06/2023 | PDSD Application Completeness Express | REVIEW COMPLETED |