Permit: TC-COM-0223-00715
Permit Details
Status:
In Review
Type:
Commercial Building
Address:
3920 N SUN TRAN BL
Address NEW:
3920 N SUN TRAN BL
Apply Date:
02/24/2023
Applicant:
Anthony Baiady
Description:
Construction of new Compressed Natural Gas control building and related site improvements. Special inspection required for Outdoor Lighting.
Permit Reviews
Permit Number - TC-COM-0223-00715
Permit Status: In review
Permit Description: Construction of new Compressed Natural Gas control building and related site improvements. Special inspection required for Outdoor Lighting.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 09/26/2023 | COMMERCIAL REVIEW - FULL v.4 | 10/18/2023 | APPROVED |
| 05/24/2023 | COMMERCIAL REVIEW - FULL v.2 | 06/29/2023 | REQUIRES RESUBMIT |
| 02/12/2026 | COMMERCIAL REVIEW - FULL v.1 | 03/02/2026 | APPROVED |
| 08/21/2023 | COMMERCIAL REVIEW - FULL v.3 | 09/18/2023 | REQUIRES RESUBMIT |
| 10/18/2023 | RESTAMP - COMMERCIAL v.1 | 10/25/2023 | APPROVED |
| 03/06/2023 | COMMERCIAL REVIEW - FULL v.1 | 04/20/2023 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TC-COM-0223-00715
Permit Status: In review
Permit Description: Construction of new Compressed Natural Gas control building and related site improvements. Special inspection required for Outdoor Lighting.
Total Outstanding Activity Conditions - 8
| Date | Name |
|---|---|
| 02/12/2026 | SPECIAL INSPECTION OF CONCRETE IS REQUIRED. |
| 02/12/2026 | SPECIAL INSPECTION OF MASONRY IS REQUIRED. |
| 02/12/2026 | SPECIAL INSPECTION OF SOILS IS REQUIRED. |
| 06/16/2026 | A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit. |
| 06/22/2023 | AIR BALANCING REPORT IS REQUIRED. |
| 06/29/2023 | SPECIAL INSPECTION FOR OUTDOOR LIGHTING IS REQUIRED. |
| 10/23/2023 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
| 10/23/2023 | SPECIAL INSPECTION FOR WELDING IS REQUIRED. |
Conditions
Permit Number - TC-COM-0223-00715
Permit Status: In review
Permit Description: Construction of new Compressed Natural Gas control building and related site improvements. Special inspection required for Outdoor Lighting.
| Date | Description | Comments |
|---|---|---|
| 10/25/2023 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
| 10/23/2023 | This project requires the completion of a Fire Construction Permit PRIOR TO FINALING this permit. |
Outstanding Inspections
Permit Status: In Review
Permit Number: TC-COM-0223-00715
Permite Description: Construction of new Compressed Natural Gas control building and related site improvements. Special inspection required for Outdoor Lighting.
Total Outstanding Inspections - 6
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/29/2026 | COT - LCBU - Preslab | N/A | Not Ready | |
| 09/18/2026 | COT - LCEL - Grounding/Bonding | N/A | Partial Pass | |
| 10/15/2026 | COT - LCPL - Plumbing Intermediate | N/A | Partial Pass | |
| 10/26/2026 | COT - LCEL - Electrical Underground | N/A | Partial Pass | |
| 11/02/2026 | zzzPDSD Building Division - Site Excavation/Layout/Rebar | N/A | Not Ready | |
| 11/06/2026 | COT - HCBU - Masonry Pregrout | N/A | Partial Pass | CNG Control building. 3rd lift at all perimeter walls approved. Corrections have been made per previous notes. Okay to grout all progress areas. 12’ cmu wall per key note 11 on page C200. 1st lift at Walls between both equipment pads CNG pad. North to south and heading east. Okay to grout all progress areas. Approved per detail 110 page S3.0 11/6/2026 |
Completed Inspections
Permit Status: In Review
Permit Number: TC-COM-0223-00715
Permit Description: Construction of new Compressed Natural Gas control building and related site improvements. Special inspection required for Outdoor Lighting.
Total Completed Inspections - 2
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/17/2026 | COT - LCPL - Rough Soil | Passed | Okay to backfill. Shading required. 6/12/2026 | |
| 06/17/2026 | COT - HCBU - Stem Wall/Retaining Wall | Passed | Reinforcements at stem walls approved. All perimeter walls included. Okay to grout progress areas. 6/12/2026 |