Permit Number: TC-COM-0223-00664
Parcel: 10821328B

Review Status: Requires Resubmit

Review Details: COMMERCIAL REVIEW - FULL v.2

Permit Number - TC-COM-0223-00664
Review Name: COMMERCIAL REVIEW - FULL v.2
Review Status: Requires Resubmit
Review Date Reviewer's Name Type of Review Description Status Comments
05/12/2023 Bldg Permits - Post Review PENDING ASSIGNMENT
05/12/2023 External Reviewers - SAFEBuilt REQUIRES RESUBMIT Activity Number: TC-COM-0223-00664

Structural(S) Reviewer
Daljit Benipal
dbenipal@safebuilt.com
Denied
Reason:
Date Completed : 5/12/2023 9:05:43 AM
RESPONSE LETTER IS SUBMITTED WHICH SAYS "SEE ATTACHED STRUCTURAL CALCULATIONS FOR ROOF SUPPORTED MEMBERS AS REQUESTED"
NO STRUCTURAL CALCULATIONS SUBMITTED FOR REVIEW IN THIS SUBMITTED. RESUBMIT STRUCTURAL CALCULATIONS AS LISTED BELOW:
1. New 7 Condensing Units HP-1 thru HP-7 weighing up to 292 pounds, one Outdoor Unit ODU-1 weighing 93 pounds and a Fan weighing 29 pounds is added at existing roof (Refer to Drawings M-101, M-201 and A-530). Provide Structural Calculations for the Roof Supporting members checking their adequacy to carry additional loads from these new units.
2. All Calculations shall be sealed and signed by Professional Engineer registered with State of Arizona per Section 107.1 of International Building Code 2018.
Submit a response letter addressing these correction items and provide bubbles on the revisions to the drawings.

Building(B) Reviewer (from previous submittal TUC9197001.031623)
Andrew Bevis
abevis@safebuilt.com
Approved
Reason:
Date Completed : 3/28/2023 11:42:10 AM

Mechanical(M) Reviewer
Neil Samaan
nsamaan@safebuilt.com
Approved with Comments
Reason:
Date Completed : 5/4/2023 9:09:10 PM
1. Where duct penetrates more than 2 stories it shall be protected by a shaft for the bathroom exhaust on sheet M-100 separation between B & E occupancy in table 508.4 of the IBC requires a 1 hour separation (IMC2018,607.6.1) Complied
2. Appliances installed on roof's above 16" from grade shall be provided with an approved permanent means of access sheet M-101 (IMC2018306.5) Complied
3. on your ventilation outside air schedule for room #108 you got required outside airflow at 283 cfm's but AHU-1 is only bringing in 240cfm's. Complied also the total air required for AHU-2 total required air is 222cfm and your only bringing in 205cfm's also AHU-4 required is 320 cfm's your only bringing in 300 cfm's please correct pm sheet M-201 (IMC2018,403.3.1.1.1)
All corrections complied
Approved/subject to field approval

Electrical(E) Reviewer (from previous submittal TUC9197001.031623)
Ron Ross
rross@safebuilt.com
Approved with Comments
Reason:
Date Completed : 3/27/2023 10:26:11 AM
Electrical Review of Fusion
By: Ron Ross PE
FYI for future submittals for Tucson: Tucson require’s short circuit calculations for panels to confirm that KAIC ratings are sufficient for new panels.
This review is approved as Panel's were spec'd at 22 KAIC, a value 2x higher than standard 240 VAC rated panels.

Plumbing(P) Reviewer
Perry Hendershott
phendershott@safebuilt.com
Approved with Comments
Reason:
Date Completed : 5/3/2023 9:19:32 PM
Second Plumbing Review: OK Subject to Field Inspections
1). water piping sizing calculations used on plan page P-100 = IPC 604.1
04/21/2023 PDSD Application Completeness REVIEW COMPLETED