Review Status: Requires Resubmit
Review Details: COMMERCIAL REVIEW - FULL v.2
Permit Number - TC-COM-0223-00664
Review Name: COMMERCIAL REVIEW - FULL v.2
Review Status: Requires Resubmit
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
05/12/2023 | Bldg Permits - Post Review | PENDING ASSIGNMENT | |||
05/12/2023 | External Reviewers - SAFEBuilt | REQUIRES RESUBMIT | Activity Number: TC-COM-0223-00664 Structural(S) Reviewer Daljit Benipal dbenipal@safebuilt.com Denied Reason: Date Completed : 5/12/2023 9:05:43 AM RESPONSE LETTER IS SUBMITTED WHICH SAYS "SEE ATTACHED STRUCTURAL CALCULATIONS FOR ROOF SUPPORTED MEMBERS AS REQUESTED" NO STRUCTURAL CALCULATIONS SUBMITTED FOR REVIEW IN THIS SUBMITTED. RESUBMIT STRUCTURAL CALCULATIONS AS LISTED BELOW: 1. New 7 Condensing Units HP-1 thru HP-7 weighing up to 292 pounds, one Outdoor Unit ODU-1 weighing 93 pounds and a Fan weighing 29 pounds is added at existing roof (Refer to Drawings M-101, M-201 and A-530). Provide Structural Calculations for the Roof Supporting members checking their adequacy to carry additional loads from these new units. 2. All Calculations shall be sealed and signed by Professional Engineer registered with State of Arizona per Section 107.1 of International Building Code 2018. Submit a response letter addressing these correction items and provide bubbles on the revisions to the drawings. Building(B) Reviewer (from previous submittal TUC9197001.031623) Andrew Bevis abevis@safebuilt.com Approved Reason: Date Completed : 3/28/2023 11:42:10 AM Mechanical(M) Reviewer Neil Samaan nsamaan@safebuilt.com Approved with Comments Reason: Date Completed : 5/4/2023 9:09:10 PM 1. Where duct penetrates more than 2 stories it shall be protected by a shaft for the bathroom exhaust on sheet M-100 separation between B & E occupancy in table 508.4 of the IBC requires a 1 hour separation (IMC2018,607.6.1) Complied 2. Appliances installed on roof's above 16" from grade shall be provided with an approved permanent means of access sheet M-101 (IMC2018306.5) Complied 3. on your ventilation outside air schedule for room #108 you got required outside airflow at 283 cfm's but AHU-1 is only bringing in 240cfm's. Complied also the total air required for AHU-2 total required air is 222cfm and your only bringing in 205cfm's also AHU-4 required is 320 cfm's your only bringing in 300 cfm's please correct pm sheet M-201 (IMC2018,403.3.1.1.1) All corrections complied Approved/subject to field approval Electrical(E) Reviewer (from previous submittal TUC9197001.031623) Ron Ross rross@safebuilt.com Approved with Comments Reason: Date Completed : 3/27/2023 10:26:11 AM Electrical Review of Fusion By: Ron Ross PE FYI for future submittals for Tucson: Tucson require’s short circuit calculations for panels to confirm that KAIC ratings are sufficient for new panels. This review is approved as Panel's were spec'd at 22 KAIC, a value 2x higher than standard 240 VAC rated panels. Plumbing(P) Reviewer Perry Hendershott phendershott@safebuilt.com Approved with Comments Reason: Date Completed : 5/3/2023 9:19:32 PM Second Plumbing Review: OK Subject to Field Inspections 1). water piping sizing calculations used on plan page P-100 = IPC 604.1 |
||
04/21/2023 | PDSD Application Completeness | REVIEW COMPLETED |