Permit Review Detail
Review Status: Requires Resubmit
Review Details: COMMERCIAL REVIEW - FULL v.2
Permit Number - TC-COM-0124-00042
Review Name: COMMERCIAL REVIEW - FULL v.2
Review Status: Requires Resubmit
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
01/12/2024 | Site Zoning | APPROVED | |||
01/22/2024 | Water - PDSD | APPROVED | |||
01/23/2024 | Site Engineering | NOT REQUIRED | |||
01/23/2024 | Bldg Permits - Post Review | PENDING ASSIGNMENT | |||
01/22/2024 | Commercial Electrical | REQUIRES RESUBMIT | Please address the electrical plan review comments and provide a written response. 1. Plan sheets A1.01 and ID1.01 both show a new electrical panel. The electrical plans show the electrical panel as existing. Please clarify. Ref; 2018 IBC section 107.2.1, 2017 NEC |
||
01/22/2024 | Commercial Mechanical | REQUIRES RESUBMIT | Revise the mechanical design as required to avoid using the vestibule as a return air duct and as a source of outside air for the restroom exhaust fan. Reference: Section 601.2, IMC 2018. | ||
01/22/2024 | Commercial Plumbing | REQUIRES RESUBMIT | Clarify the specification for the metering faucet for the lavatory (the Plumbing Fixture Schedule calls out a non-metering, discontinued faucet) The Low Flow Requirements description calls for a faucet dispensing a maximum of 0.25 gallons per metering cycle but does not indicate that the faucet cycle must last for at least 10-seconds for accessibility. Reference: Section 419.6, IPC 2018, as amended by the City of Tucson and Section 606.4, ICC/ANSI A117.1-09. | ||
01/22/2024 | Commercial Structural | REQUIRES RESUBMIT | Please submit your revised drawings along with a detailed response letter, which states how all Building Review Section comments were addressed. 1. Please provide an architectural site plan showing all buildings or structures on the lot and show the exterior accessible route to the accessible entrance from the accessible parking space(s) IBC 107.2.6 2. Please amend plans to show the paths of egress and show the path of egress does not pass through kitchens, storage rooms, or similar spaces. IBC 107.2.3, IBC 1016.2 3. Please provide a photometric plan or other method of showing 1 footcandle of normal power illumination at the walking surface along the path(s) of exit discharge, while the building is occupied. IBC 1008.2.1, IBC 1008.2.3 4. Please amend plans to show Exit signs at doors, as required to direct egress. IBC 1013.1 5. Please amend plan to add a sign above the exterior entry doors: This Door To Remain Unlocked When This Space Is Occupied. IBC 1010.1.9.4 6. Provide adequate notes or details on the plans or provide a door schedule to show that the entry door is accessible in accordance with ANSI Section 404. Provide complete specifications for the door and door hardware within the plan set. For example, door hardware 404.2.6, closing speed 404.2.7, door opening force 404.2.8, door surface 404.2.9, etc. 7. Please amend plans to show how the breakroom sink complies with ANSI 804 and 606. For example, is this a front approach where the toe kicks are attached to the doors? 8. Amend wall details plans to note or otherwise indicate the method of fastening and bracing new walls at the ceiling or roof connection. Additionally, provide a wall type detail for each new wall to include, but not be limited to, interior wall coverings and finishes. IBC 107.2.1 9. Further, related if applicable, please provide engineering to show how unbraced interior walls and partitions that exceed 6 feet in height, including finish materials, shall have adequate strength and stiffness to resist the loads to which they are subjected but not less than a horizontal load of 5 psf. IBC 1607.15. 10. Please clarify if any ceiling demolition will occur. If so, provide ceiling demolition plan or otherwise provide ceiling demolition information within the plan set. IBC 107.2.1. Further, if new ceiling is to be installed, provide drawing details to show new ceiling construction. IBC 107.2.1 11. Please provide details for any penetration firestops that are to be used with this construction. Please amend plans to ensure entire approved, listed assembly is shown on the drawings. IBC 714.1 Mark Masek Plans Examiner Mark.masek@tucsonaz.gov 520-837-4994 |
||
01/19/2024 | Fire New Construction | REVIEW COMPLETED | |||
01/11/2024 | PDSD Application Completeness | REVIEW COMPLETED |