Permit Review Detail
Review Status: Approved
Review Details: COMMERCIAL REVIEW - FULL v.2
Permit Number - TC-COM-0123-00558
Review Name: COMMERCIAL REVIEW - FULL v.2
Review Status: Approved
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
06/27/2023 | External Reviewers - SAFEBuilt | APPROVED | Activity Number: TC-COM-0123-00558 GENERAL: Provide written responses to all review comments. Provide a complete plan set. Provide additional documents as requested by review staff. Structural(S) Reviewer Daljit Benipal dbenipal@safebuilt.com Conditionally Aproved Reason: Date Completed : 2/28/2023 3:33:08 PM NOTE: Every effort has been made to identify the code violations. Any oversight by the review team shall not be considered an authority to violate, set aside, cancel or alter applicable codes or ordinances. The plan review and permit issuance shall not be considered a warranty or guarantee. The Structural Engineer is responsible for following ALL applicable Federal, State and local Municipal Codes and Ordinances. Building(B) Reviewer Andrew Bevis abevis@safebuilt.com Conditionally Approved Reason: Date Completed : 6/6/2023 9:02:22 AM 1. The amount of accessible seating that has been provided is correct. However, the distribution should be include all experiences. Provide accessible seating at the bar in accordance with Section 226.1 and 226.2 of the 2010 ADAAG Mechanical(M) Reviewer Neil Samaan nsamaan@safebuilt.com Conditionally Approved Reason: Date Completed : 2/10/2023 6:13:52 PM Approved/subject to field approval Electrical(E) Reviewer Ron Ross rross@safebuilt.com Approved Reason: Date Completed : 6/15/2023 8:01:50 PM Plumbing(P) Reviewer Perry Hendershott phendershott@safebuilt.com Conditionally Approved Reason: Date Completed : 6/17/2023 8:18:22 AM Second Plumbing Review: OK Subject To Field Inspections** 1). OK- SS.17 Ice maker on plan page P1.0 can't discharge to the grease system -IPC 1003.2** GB50 interceptor ok to receive ice mach. discharge per Pima Utility authority see attached letter in documents tab** 2). OK-FC4 condensate on plan page P1.0 can't discharge to the grease system -IPC 1003.2 ** Re-Routed to exterior will need trap , subject to field inspections** IPC 314.2.1, 314.2.4 3). OK-Per Tucson plumbing code amendments, No more than four items can discharge to a Hydromechanical grease interceptor . Update plan page P1.0** GB50 interceptor ok per Pima Utility authority see attached letter in documents tab** 4).OK-Add grease interceptor calculations to plan page P1.0 or P2.0 -Tucson Plumbing Code Amendments** GB50 interceptor ok per Pima Utility authority see attached letter in documents tab** |
||
06/27/2023 | Bldg Permits - Post Review | REVIEW COMPLETED | |||
06/05/2023 | PDSD Application Completeness | REVIEW COMPLETED |