Permit Review Detail
Review Status: Requires Resubmit
Review Details: COMMERCIAL REVIEW - FULL v.2
Permit Number - T22CM07804
Review Name: COMMERCIAL REVIEW - FULL v.2
Review Status: Requires Resubmit
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 01/14/2023 | Bldg Permits - Post Review Express | PENDING ASSIGNMENT | |||
| 01/14/2023 | External Reviewers - SAFEBuilt | REQUIRES RESUBMIT | Activity Number: T22CM07804 GENERAL: Provide written responses to all review comments. Provide a complete plan set. Provide additional documents as requested by review staff. STRUCTURAL REVIEW COMMENTS: Conditionally Approved NOTE: Every effort has been made to identify the code violations. Any oversight by the review team shall not be considered an authority to violate, set aside, cancel or alter applicable codes or ordinances. The plan review and permit issuance shall not be considered a warranty or guarantee. The Structural Engineer is responsible for following ALL applicable Federal, State and local Municipal Codes and Ordinances. BUILDING REVIEW COMMENTS: Conditinally Approved Conditionally approved, per the following: Every effort has been made to identify the code violations. Any oversight by the review team shall not be considered an authority to violate, set aside, cancel, or alter applicable codes or ordinances. The plan review and permit issuance shall not be considered a warranty or guarantee. The registered design professional is responsible for following ALL applicable Federal, State, and local Municipal Codes and Ordinances. MECHANICAL REVIEW COMMENTS: Denied 1. Provide ventilation air to storage room sheet M1 (IMC2018,403.3.1.1) Complied 2. Provide the CO2 amount being stored and dispensed for beverages and plan of protection (IBC2015,908.7) This location will have under 100 lbs of CO2 and is except from IFC Tucson Amendments 5307.1 CO2 under 100 lbs - noted on cover sheet A1 Complied 3. Provide manufacturers specs for hood 1 and hood 2 (IMC2018,106.3.1) Not Complied 4. Will there be a dishwasher and if so dishwasher hood specs is required (IMC2018,106.3.1) Not Complied 5. Provide refrigeration schedule including specs for walk in coolers and freezers and condensing unit information including amount and type of refrigeration (IMC2015,106.3.1) Not Complied Please provide verbal response to each correction along with the revised plans, you only resonded verbally to 1 correction ELECTRICAL REVIEW COMMENTS Conditionally Approved E4.0 ELECTRICAL PANEL SCHEDULES: Discrepancy between One Line Diagram Feeder Schedule and feeder shown between CT Can and Panel LD. PLUMBING REVIEW COMMENTS: Denied Second Plumbing Review: PLUMBING COMMENTS NOT ADDRESSED 1). SAME- The #13 Ice machine on plan page P1 can't discharge to the grease interceptor. -IPC 1003.2 2). SAME- The M4 , #18, #31 walk-in coolers condensate on plan page P1 can't discharge to the grease system. -IPC 1003.2 3). SAME- HP1, HP3, EC1 condensate on plan page P1 can't discharge to the grease system. -IPC 1003.2 4). SAME- Employee restroom door can't open into the kitchen ( suggest install door adjacent to the #20 prep sink if permissible by building review) Update all affected pages. -IPC 403.3.2 5). SAME- Hand sink next to outdoor grill on plan page P1 needs overhang above, it can't receive rain water. -IPC 1101.3 6). SAME- Hose bibs at water main entrance & behind #6 hot table need individual shut off valves. -IPC 606.2 7).SAME- Per the manufacturer website the GB-250 grease interceptor selected on plan page P6 is a hydromechanical type. The Tucson plumbing code amendments only allow 4 items to discharge to this type of grease interceptor. Update all affected plumbing pages 8).SAME- Plan page A8 needs to illustrate the primary & secondary roof drains/conductors and or Primary/secondary scuppers or gutters & downspouts along with sizes & calculations. -IPC 1106.1, 1106.2, 1106.3, 1106.6 .** STILL NOT SHOWING SECONDARY SCUPPERS** 9). TSAME- he 5 Unit Heater exhaust/intakes need to be illustrated to the termination locations within the mechanical or plumbing plans. Per the manufacturer websites these models have intake & exhaust connections. -IFGC 305.1, 304, 503.1 10). SAME- label the fuel source of the #15 outdoor grill on plan page P3- IFGC 106.3.1 11). SAME- Plan set needs to be accompanied by the site utility piping plan for the continuation of sewer, storm, water service to show correlation with plan pages P1 & P2 . -IPC 106.3.1 12). SAME- Plan page P6 fixture schedule missing mop sink manufacturer name & model number & missing mop sink faucet info. -IPC 303 13).SAME- Plan Page A7 needs to include restroom fixture to fixture center separation distances along with side wall to fixture center measurements. -IPC 404.2, 405.3.1 ** STILL NEED LAV DISTANCE** If you require additional clarification regarding these comments, please contact Doris Benoit at doris.benoit@tucsonaz.gov |
||
| 01/13/2023 | Site Engineering | REQUIRES RESUBMIT | See Zoning Comment | ||
| 01/09/2023 | Site Zoning | REQUIRES RESUBMIT | ZONING REVIEW TRANSMITTAL FROM: Wyatt Berger Planner PROJECT: T22CM07804 5201 S 12th Av New Food Service building (2nd Review) TRANSMITTAL DATE: January 09, 2023 COMMENTS: Please resubmit revised drawings and any redlined plans along with a detailed response letter, which states how all Zoning Review Section comments were addressed. 1. Zoning has reviewed the building plans for compliance with DP22-0124. Although it appears that the building plan matches the DP, Zoning cannot approve the building plan until the DP is approved. If you have any questions about this transmittal, please contact Wyatt Berger at Wyatt.Berger@tucsonaz.gov. | ||
| 01/11/2023 | Fire New Construction | REVIEW COMPLETED | |||
| 12/22/2022 | PDSD Application Completeness Express | REVIEW COMPLETED |