Permit Review Detail
Review Status: Requires Resubmit
Review Details: BUILDING DEFERRED SUBMITTAL REVIEW v.1
Permit Number - T21CM09907
Review Name: BUILDING DEFERRED SUBMITTAL REVIEW v.1
Review Status: Requires Resubmit
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
04/18/2024 | Bldg Permits - Post Review | PENDING ASSIGNMENT | |||
04/12/2024 | Concrete Installation Inspection (Deferred Submittal) | REQUIRES RESUBMIT | Concrete specification strength test results FAILED on 9/18/23, 4/11/23, 4/6/23 and 12/22/22 lab ID 222070M26 some as low as 65% of required strength. Please have Project Structural Engineer review and obtain his recommendation (should he/she decides to approve this report, a seal/signature/date will be required on each report along with his statement for accepting the test result). | ||
04/18/2024 | External Reviewers - SAFEBuilt | REQUIRES RESUBMIT | DEFERRED SUBMITTAL ELEVATOR Structural(S) Reviewer Kimiyoshi Shimabukuro kshimabukuro@safebuilt.com Denied Reason: Date Completed : 4/16/2024 11:23:35 AM 1) Shop drawings are not coordinated per RKAA designer marked up comments. 2) Stair headroom clearance less than 80 inches is shown at 6’-4” (76.5”). 2018 IBC section1011.3 Headroom. “Stairways shall have a headroom clearance of not less than 80 inches (2032 mm) measured vertically from a line connecting the edge of the nosings. Such headroom shall be continuous above the stairway to the point where the line intersects the landing below, one tread depth beyond the bottom riser. The minimum clearance shall be maintained the full width of the stairway and landing.” Building(B) Reviewer Kimiyoshi Shimabukuro kshimabukuro@safebuilt.com Denied Reason: Date Completed : 4/16/2024 11:23:58 AM 1) Stair plans do not show landing width. 2018 IBC section 1011.6 Stairway landings. “There shall be a floor or landing at the top and bottom of each stairway. The width of landings, measured perpendicularly to the direction of travel, shall be not less than the width of stairways served. Every landing shall have a minimum depth, measured parallel to the direction of travel, equal to the width of the stairway or 48 inches (1219 mm), whichever is less.’ 2) Stair plans shows tread less than 11 inch (9 ¼”, 10 3/8”). 2018 IBC section 1011.5.2 Riser height and tread depth. “Stair riser heights shall be 7 inches (178 mm) maximum and 4 inches (102 mm) minimum. The riser height shall be measured vertically between the nosings of adjacent treads. Rectangular tread depths shall be 11 inches (279 mm) minimum measured horizontally between the vertical planes of the foremost projection of adjacent treads and at a right angle to the tread’s nosing.” |
||
04/18/2024 | External Reviewers - SAFEBuilt | REQUIRES RESUBMIT | DEFERRED SUBMITTAL STAIR DESIGN Structural(S) Reviewer Kimiyoshi Shimabukuro kshimabukuro@safebuilt.com Denied Reason: Date Completed : 4/16/2024 11:23:35 AM 1) Shop drawings are not coordinated per RKAA designer marked up comments. 2) Stair headroom clearance less than 80 inches is shown at 6’-4” (76.5”). 2018 IBC section1011.3 Headroom. “Stairways shall have a headroom clearance of not less than 80 inches (2032 mm) measured vertically from a line connecting the edge of the nosings. Such headroom shall be continuous above the stairway to the point where the line intersects the landing below, one tread depth beyond the bottom riser. The minimum clearance shall be maintained the full width of the stairway and landing.” Building(B) Reviewer Kimiyoshi Shimabukuro kshimabukuro@safebuilt.com Denied Reason: Date Completed : 4/16/2024 11:23:58 AM 1) Stair plans do not show landing width. 2018 IBC section 1011.6 Stairway landings. “There shall be a floor or landing at the top and bottom of each stairway. The width of landings, measured perpendicularly to the direction of travel, shall be not less than the width of stairways served. Every landing shall have a minimum depth, measured parallel to the direction of travel, equal to the width of the stairway or 48 inches (1219 mm), whichever is less.’ 2) Stair plans shows tread less than 11 inch (9 ¼”, 10 3/8”). 2018 IBC section 1011.5.2 Riser height and tread depth. “Stair riser heights shall be 7 inches (178 mm) maximum and 4 inches (102 mm) minimum. The riser height shall be measured vertically between the nosings of adjacent treads. Rectangular tread depths shall be 11 inches (279 mm) minimum measured horizontally between the vertical planes of the foremost projection of adjacent treads and at a right angle to the tread’s nosing.” Mechanical N/A Electrical N/A Plumbing N/A |
||
04/10/2024 | Other Inspection Reports (Deferred Submittal) | REQUIRES RESUBMIT | FIRE ALARM As-Built drawings with revisions relocating and adding detectors NOT SUBMITTED TO TUCSON FIRE for their record. Please submit to Tucson Fire Department allowing them to update their record drawings replacing your previously approved submittal. See Fire Alarm permit TF-FCP-0223-00427 inspection passed 1/23/24. |
||
04/12/2024 | Masonry Inspection (Deferred Submittal) | REVIEW COMPLETED | |||
04/10/2024 | Other Inspection Reports (Deferred Submittal) | REVIEW COMPLETED | FIRE SPRINKLER see fire sprinkler permit TF-FCP-0323-00489 inspection passed 1/19/24 |
||
04/12/2024 | Other Inspection Reports (Deferred Submittal) | REVIEW COMPLETED | FIELD WELDING | ||
04/12/2024 | Other Inspection Reports (Deferred Submittal) | REVIEW COMPLETED | HIGH STRENGTH BOLTS INSTALLED IN CONCRETE | ||
04/12/2024 | Other Inspection Reports (Deferred Submittal) | REVIEW COMPLETED | REINFORCING STEEL AND/OR PRE-STRESSING TENDONS | ||
04/12/2024 | Other Inspection Reports (Deferred Submittal) | REVIEW COMPLETED | STEEL FRAME SPECIAL MOMENT RESISTING | ||
04/10/2024 | PDSD Application Completeness | REVIEW COMPLETED | |||
04/12/2024 | Piling/Caisson Inspection (Deferred Submittal) | REVIEW COMPLETED | |||
04/12/2024 | Post-Installed Anchor Inspection (Deferred Submittal) | REVIEW COMPLETED | |||
04/10/2024 | Site Prep Inspection (Deferred Submittal) | REVIEW COMPLETED | EXCAVATION/GRADING/FILL | ||
04/12/2024 | Welding Inspection (Deferred Submittal) | REVIEW COMPLETED |