Permit Review Detail
Review Status: Requires Resubmit
Review Details: BUILDING DEFERRED SUBMITTAL REVIEW v.1
Permit Number - T21CM04894
Review Name: BUILDING DEFERRED SUBMITTAL REVIEW v.1
Review Status: Requires Resubmit
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 11/09/2023 | Masonry Inspection (Deferred Submittal) Express | APPROVED | |||
| 11/09/2023 | Site Prep Inspection (Deferred Submittal) Express | APPROVED | |||
| 11/02/2023 | Water Sterilization Report (Deferred Submittal) Express | APPROVED | |||
| 11/09/2023 | Bldg Permits - Post Review Express | PENDING ASSIGNMENT | |||
| 11/09/2023 | Concrete Installation Inspection (Deferred Submittal) Express | REQUIRES RESUBMIT | 7/7/2023 concrete test results in August 11,2023 report for slab on grade at front patio location indicates a test result (3028 psi average) which is less than the required concrete design strength (4000 psi) indicated by the Structural Drawings. Please have Engineer of Record evaluate and remedy this deviation form the design requirements and resubmit. NOTE: This also applies on specimen 26 test date 7/28/2023 showing strength at 3220 psi is lower than the design strength of 4000 psi | ||
| 11/02/2023 | PDSD Application Completeness Express | REVIEW COMPLETED | |||
| 11/09/2023 | Post-Installed Anchor Inspection (Deferred Submittal) Express | REVIEW COMPLETED |