| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 01/23/2023 | OK to Submit - Zoning Fast | NOT REQUIRED | |||
| 02/02/2023 | CDRC Post Review Express | PENDING ASSIGNMENT | |||
| 02/02/2023 | CDRC Review Coordinator Express | PENDING ASSIGNMENT | |||
| 02/02/2023 | Site Engineering | PENDING ASSIGNMENT | |||
| 02/02/2023 | OK to Submit - Engineering Fast | REQUIRES RESUBMIT | Based on the photos provided by the inspector and the approved plans, the following must be addressed on this site: The basin pipe outlets are shown as flush with the face of the gabions. The installation is not consistent with this. The discharges to the wash are eroding the soil in the bed. The erosion The basin is not infiltrating stormwater in a timely manner. The engineer of record needs to provide direction for fixing the basin and provide direction for ongoing maintenance. Once these have been addressed, the Engineer of Record should resubmit his certification letter with an explanation for the changes made. |
||
| 01/23/2023 | CDRC Application Completeness Express | REVIEW COMPLETED |