Plan Review Detail
Review Status: Requires Resubmit
Review Details: CIP - DEVELOPMENT SITE - FINAL v.1
Plan Number - CIP-0725-00016
Review Name: CIP - DEVELOPMENT SITE - FINAL v.1
Review Status: Requires Resubmit
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| NPPO | APPROVED | ||||
| Site Engineering | APPROVED | ||||
| Site Landscape | APPROVED | ||||
| TW Planning and Engineering Review | APPROVED | CONDITIONALLY APPROVED: Please see notes on sheets 32-35 and 43-45. Previous comments on Landscaping been made and not corrected on these 100% plans. Please add my contact information on sheet 46 should any issues arise during trenching. | |||
| CDRC Post Review Express | REQUIRES RESUBMIT | Please address reviewers' comments for the next submittal. NOTE: If any of the following apply, a Fugitive Dust Activity Permit is required from the Pima County Department of Environmental Quality (PDEQ). Earthmoving or Land Clearing over 1 acre Trenching over 300 feet for utility installation or repair Road construction over 50 feet Blasting Please contact the following to obtain your permit. Fugitive Dust Activity Permit: Contact Pima County ADEQ at (520) 724-7400 https://www.pima.gov/596/Fugitive-Dust Once received you may upload your permit to the attachment section along with any external reviewer approval letters. If you have any questions regarding this information, please contact Sonya Bermudez at sonya.bermudez@tucsonaz.gov or 520-730-7979. |
|||
| CDRC Application Completeness Express | REVIEW COMPLETED | ||||
| External Reviewers - Tucson Electric Power (TEP) | REVIEW COMPLETED | May 13, 2026 WO#T164437 City of Tucson Planning and Development Services Attn: CDRC Admin Team Dear CDRC Admin Team Subject: DELL URICH GOLF COURSE AND 22ND STREET MULTI-USE PATH IMPROV CIP-0725-00016 Tucson Electric Power Company (TEP) has reviewed and approved the development plan submitted 4/28/2026. There are existing facilities within the development which are depicted upon the plan. TEP pole line does not appear to be in conflict. Please call Design if relocation is required. Enclosed is a copy of a TEP facilities map showing the approximate location of the existing facilities. Any relocation costs will be billable to the customer. To apply for electric service, please call the New Construction department at (520) 918-8300. Please submit a final set of plans including approved site, electric load, paving off-site improvements and irrigation plans. If available, include a PDF version of the plans. Questions regarding Land, ROW, Easement, etc., please contact the TEP Land Department Liz Boehler Right of Way Agent Consultant 520-686-1341 Landreviews@tep.com Should you have any technical questions, please contact the area designer, Martin Salazar (520) 305-6713 msalazar@tep.com Sincerely, Design Admins Design Admins Tucson Electric Power |
|||
| Fire New Construction | REVIEW COMPLETED | ||||
| Historic | REVIEW COMPLETED | A Class III survey has been conducted for this project. It will not adversely impact cultural resources. | |||
| New Services/JOC | REVIEW COMPLETED | ||||
| ROW Engineering Review | REVIEW COMPLETED | ||||
| Site Zoning | REVIEW COMPLETED | FROM: Bobby Parsons PDSD Zoning Review Section PROJECT: CIP-0725-00016 600 S ALVERNON WY TUCSON, AZ 85711 Dell Urich Golf Course Walking Path (3rd Review) (CIP Final Review) TRANSMITTAL DATE: May 13, 2026 COMMENTS: Resubmit revised drawings along with a detailed response letter, which states how all Zoning Review Section comments were addressed. 1. Comment: Follow up to previous comment 2. After consulting with Nicholas Ross (Site Zoning Section Manager), please obtain a City Managers Office (CMO) waiver for the 8’ high chain link fence topped with a 20’ high mesh netting totaling 28’ as noted on Sheet G-002. If you have any questions about this transmittal, please contact Robert.Parsons@tucsonaz.gov |
|||
| Traffic Engineering Review | REVIEW COMPLETED | No traffic concerns in regard to this multi-use path project. No comments. | |||
| Water - PDSD | REVIEW COMPLETED |