Plan Number: CIP-0725-00016
Parcel: 12620001C

Review Status: Requires Resubmit

Review Details: CIP - DEVELOPMENT SITE - FINAL v.1

Plan Number - CIP-0725-00016
Review Name: CIP - DEVELOPMENT SITE - FINAL v.1
Review Status: Requires Resubmit
Review Date Reviewer's Name Type of Review Description Status Comments
NPPO APPROVED
Site Engineering APPROVED
Site Landscape APPROVED
TW Planning and Engineering Review APPROVED CONDITIONALLY APPROVED: Please see notes on sheets 32-35 and 43-45. Previous comments on Landscaping been made and not corrected on these 100% plans. Please add my contact information on sheet 46 should any issues arise during trenching.
CDRC Post Review Express REQUIRES RESUBMIT Please address reviewers' comments for the next submittal.
NOTE:
If any of the following apply, a Fugitive Dust Activity Permit is required from the Pima County Department of Environmental Quality (PDEQ).

Earthmoving or Land Clearing over 1 acre

Trenching over 300 feet for utility installation or repair

Road construction over 50 feet

Blasting

Please contact the following to obtain your permit.

Fugitive Dust Activity Permit: Contact Pima County ADEQ at (520) 724-7400

 https://www.pima.gov/596/Fugitive-Dust

Once received you may upload your permit to the attachment section along with any external reviewer approval letters. If you have any questions regarding this information, please contact Sonya Bermudez at sonya.bermudez@tucsonaz.gov or 520-730-7979.
CDRC Application Completeness Express REVIEW COMPLETED
External Reviewers - Tucson Electric Power (TEP) REVIEW COMPLETED May 13, 2026
WO#T164437
City of Tucson
Planning and Development Services
Attn: CDRC Admin Team
Dear CDRC Admin Team
Subject: DELL URICH GOLF COURSE AND 22ND STREET MULTI-USE PATH IMPROV
CIP-0725-00016
Tucson Electric Power Company (TEP) has reviewed and approved the development plan submitted 4/28/2026. There are existing facilities within the development which are depicted upon the plan. TEP pole line does not appear to be in conflict. Please call Design if relocation is required.
Enclosed is a copy of a TEP facilities map showing the approximate location of the existing facilities. Any relocation costs will be billable to the customer.
To apply for electric service, please call the New Construction department at (520) 918-8300. Please submit a final set of plans including approved site, electric load, paving off-site improvements and irrigation plans. If available, include a PDF version of the plans.
Questions regarding Land, ROW, Easement, etc., please contact the TEP Land Department Liz Boehler
Right of Way Agent
Consultant
520-686-1341
Landreviews@tep.com
Should you have any technical questions, please contact the area designer,
Martin Salazar
(520) 305-6713
msalazar@tep.com
Sincerely,
Design Admins
Design Admins
Tucson Electric Power
Fire New Construction REVIEW COMPLETED
Historic REVIEW COMPLETED A Class III survey has been conducted for this project. It will not adversely impact cultural resources.
New Services/JOC REVIEW COMPLETED
ROW Engineering Review REVIEW COMPLETED
Site Zoning REVIEW COMPLETED FROM: Bobby Parsons
PDSD Zoning Review Section

PROJECT: CIP-0725-00016
600 S ALVERNON WY TUCSON, AZ 85711
Dell Urich Golf Course Walking Path (3rd Review) (CIP Final Review)

TRANSMITTAL DATE: ‎May 13, 2026

COMMENTS: Resubmit revised drawings along with a detailed response letter, which states how all Zoning Review Section comments were addressed.

1. Comment: Follow up to previous comment 2. After consulting with Nicholas Ross (Site Zoning Section Manager), please obtain a City Managers Office (CMO) waiver for the 8’ high chain link fence topped with a 20’ high mesh netting totaling 28’ as noted on Sheet G-002.

If you have any questions about this transmittal, please contact Robert.Parsons@tucsonaz.gov
Traffic Engineering Review REVIEW COMPLETED No traffic concerns in regard to this multi-use path project.  No comments.
Water - PDSD REVIEW COMPLETED