Plan Review Detail
Review Status: Requires Resubmit
Review Details: CIP - DEVELOPMENT SITE - FINAL v.1
Plan Number - CIP-0424-00015
Review Name: CIP - DEVELOPMENT SITE - FINAL v.1
Review Status: Requires Resubmit
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
CDRC Post Review | REQUIRES RESUBMIT | Resubmittal is required for CIP Final Review due to lack of external review approvals, dust permit requirements, and must address all reviewer comments prior to allowing the completion of the CIP process. If you have questions please reach out to Sonya or Aaron at CDRC@tucsonaz.gov. | |||
Floodplain Administration Review | REQUIRES RESUBMIT | No Review Uploaded by Elizabeth Liebold of Floodplain - Review Cycled Closed out by Matthew Carlton at request of City PM. | |||
ROW Engineering Review | REQUIRES RESUBMIT | Design Plan: See comments on Design Plans, recommend having a meeting between DTM reviewers, Environmental Services project manager and design consultant. |
|||
Traffic Engineering Review | REQUIRES RESUBMIT | Traffic Engineering comments marked up on Sheets 107-111 (RD21 - RD25). The plans already had some red markups embedded in the PDF, mostly regarding YDS4-D40/D40 striping. We agree with those comments, too. | |||
Transportation Maps and Records Review | REQUIRES RESUBMIT | No Review Uploaded by DTM - Review Cycled Closed out by Matthew Carlton at request of City PM. | |||
TW Planning and Engineering Review | REQUIRES RESUBMIT | Our understanding is that the use of wells for source water will not be approved by AWWR source water regulators. Please submit master plan to new area development showing connections to existing water system. Management level coordination required between agencies regarding this project. | |||
CDRC Application Completeness | REVIEW COMPLETED | ||||
External Reviewers - COT Parks & Recreation | REVIEW COMPLETED | Approved Regarding CIP-0424-00015, the City of Tucson Parks and Recreation Department has no additional requirements for the CIP project and no further reviews by TPRD are required. Description: Los Reales Phase 1 Linear Trail and intersection improvement Address: 5300 E. Los Reales Rd, Tucson AZ 85756 Regards, Joe Barr Project Manager Tucson Parks and Recreation |
|||
External Reviewers - Tucson Electric Power (TEP) | REVIEW COMPLETED | Good afternoon, CDRC Admin Support, TEP has reviewed your stamped plan sets for the Los Reales Sustainability Public Improvement project and found no underground or overhead facilities in conflict per plans provided. Please protect in place where applicable. Contractor to protect existing TEP poles and Underground conductors in place during construction. TEP’s overhead protection will have to be notified anytime a pole is exposed more than 12” from grade or when getting within 10' of an overhead power line. Contact Arizona 811 from anywhere in Arizona at least two full working days prior to digging. Please make sure to maintain proper separation from all TEP underground facilities when installing new facilities. Due to the file size, below is a Sharefile Link with the green sheet, plan set mark ups and clearance letter: https://uns.sharefile.com/public/share/web-s4d8e265faa6246c2aeac36a8c7b9564e [uns.sharefile.com] If you have any questions, please reach out. Thank you, Miranda Jackson, MBA Public Improvement Project Manager Resource Management Team Tucson Electric Power 520-884-3989 desk 520-449-4309 cell mjackson@tep.com |
|||
New Services/JOC | REVIEW COMPLETED | CIP-0424-00015 - CIP - Development Site - Final v1 – 5300 E LOS REALES RD Los Reales Sustainability Campus Linear Trail Phase 1 Linear trail and intersection improvement Tucson Water’s New Development offers the following comments on the submittal: All numbers and letters on the plans should be oriented to be read from either the bottom or right hand side of the sheet. On several sheets, I noticed the W’s in the linetype used to depict existing and proposed water mains were upside down and did not meet this requirement. Any questions, comments or concerns about these comments may be directed to: Tim Rowe, P.E., Civil Engineer Tucson Water, New Development Section 201 N. Stone Avenue, #2-220 P.O. Box 27210 Tucson, AZ 85726-7210 (520) 837-2106 tim.rowe@tucsonaz.gov |