1601 W SAINT MARYS RD
Outstanding Inspections
Permit Status:
Permit Number:
Permite Description:
Total Outstanding Inspections - 8
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/18/2013 | COT - FCON - Tank - Final | Completed | The generator tank fuel line was damaged during conduit excavation. Minimal fuel has been spilt. SW Fuel care is going to repair the line today. A line test will be done 03.19.2013 | |
06/04/2014 | COT - FCON - Underground Pressure | Completed | approved | |
06/10/2014 | COT - FOPR - Fire General Inspection | Completed | 20,000 gallon Diesel AST installed, piping and tank approved for use. | |
09/20/2019 | COT - FOPR - Tent/Structure | Completed | T19FO00751 A LA CARTE 1 TENT FOR ST MARYS PARTY. |
|
09/23/2021 | COT - FCOD - Fire Operational Permit | Completed | State License Facility - paid | |
06/15/2020 | Inspections of I-1 and I-2 occupancies, as well as day cares (child and adult) | Completed | ||
10/07/2021 | COT - Fire - Complaint | Completed | 10/6/21 ADQ PT04 was dispatched for a Fire Alarm. En route St. Mary's Hospital advised a housekeeper accidentally set it off while cleaning a pull station. I was not cancelled so continued to the scene. Upon arrival I asked to see the Fire Alarm panel. Brandon, a security guard led me to the basment area where the panel was located. The system showed a trouble alarm. I tried resetting it many times but it would not clear. I then asked to speak to someone in facilities. I spoke to Brian Hughes who is filling in as the Facilities Manager. He advised me that American Fire told him that there had been a short in the system which caused a module to need to be replaced. He thought they had already done so. He was going to contact them to get them to come out. I will send him a NOV. 10/12/21 ADQ This issue was resolved on the 7th. American Fire fixed the panel. Email with paperwork received. |
|
10/28/2021 | COT - FCOD - Fire Re-inspection | Completed |
Completed Inspections
Permit Status:
Permit Number:
Permit Description:
Total Completed Inspections - 8
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/18/2013 | COT - FCON - Tank - Final | Completed | The generator tank fuel line was damaged during conduit excavation. Minimal fuel has been spilt. SW Fuel care is going to repair the line today. A line test will be done 03.19.2013 | |
06/04/2014 | COT - FCON - Underground Pressure | Completed | approved | |
06/10/2014 | COT - FOPR - Fire General Inspection | Completed | 20,000 gallon Diesel AST installed, piping and tank approved for use. | |
09/20/2019 | COT - FOPR - Tent/Structure | Completed | T19FO00751 A LA CARTE 1 TENT FOR ST MARYS PARTY. |
|
09/23/2021 | COT - FCOD - Fire Operational Permit | Completed | State License Facility - paid | |
06/15/2020 | Inspections of I-1 and I-2 occupancies, as well as day cares (child and adult) | Completed | ||
10/07/2021 | COT - Fire - Complaint | Completed | 10/6/21 ADQ PT04 was dispatched for a Fire Alarm. En route St. Mary's Hospital advised a housekeeper accidentally set it off while cleaning a pull station. I was not cancelled so continued to the scene. Upon arrival I asked to see the Fire Alarm panel. Brandon, a security guard led me to the basment area where the panel was located. The system showed a trouble alarm. I tried resetting it many times but it would not clear. I then asked to speak to someone in facilities. I spoke to Brian Hughes who is filling in as the Facilities Manager. He advised me that American Fire told him that there had been a short in the system which caused a module to need to be replaced. He thought they had already done so. He was going to contact them to get them to come out. I will send him a NOV. 10/12/21 ADQ This issue was resolved on the 7th. American Fire fixed the panel. Email with paperwork received. |
|
10/28/2021 | COT - FCOD - Fire Re-inspection | Completed |