Plan: TW-PLAN-0426-0099
Plan Details
Status:
Approved to construct
Type:
TW CIP Planning & Engineering
Apply Date:
04/15/2026
Applicant:
Kyle
Description:
24" Emergency Transmission Main Replacement along the Sabino Wash. Phase 1 – Install a new 24-inch gate valve on the south embankment side of the project. Phase 2 – Remove the existing 24-inch HDPE pipeline and install new 24-inch DIP on the south embankment side of the project. Phase 3 – Remove the existing 24-inch HDPE pipeline and install new 24-inch DIP along Sabino Wash and on the north embankment side of the project, tying into the existing 24-inch gate valve (N-2482379) at the top of the north embankment.
Architects:
- Borderland
- Tricon Contracting Inc.
- Tricon Contracting, Inc.
- Tucson Water Planning & Engineering
- WestLand Engineering and Environmental Services, Inc.
Contractors:
Plan Reviews
Plan Number - TW-PLAN-0426-0099
Plan Status: Approved to Construct
Plan Description: 24" Emergency Transmission Main Replacement along the Sabino Wash.
Phase 1 – Install a new 24-inch gate valve on the south embankment side of the project.
Phase 2 – Remove the existing 24-inch HDPE pipeline and install new 24-inch DIP on the south embankment side of the project.
Phase 3 – Remove the existing 24-inch HDPE pipeline and install new 24-inch DIP along Sabino Wash and on the north embankment side of the project, tying into the existing 24-inch gate valve (N-2482379) at the top of the north embankment.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 06/24/2026 | TWPE 100% Design Plan Approval v.1 | APPROVED |