Description:
Opportunistic Short Main Replacement of ~200' of a 2" Galvanized Pipe ahead of a DTM pavement project. Waiting on 100% signatures - 5/19, Still waiting on DTM signatures 6/1/26 invitation to bid was sent out - 6/5. Due date is 6/22 Bid winner announced - Action pipe line, NOIA was sent, WAF created waiting on PO to send NTP and Construction permit. Contractor wants to start Aug. 1st Pre con was done - Project in construction 8/4
Architects:
- Dibble
- Tucson Water
Contractors:
Plan Reviews
Plan Number - TW-PLAN-0426-0079
Plan Status: Review Complete
Plan Description: Opportunistic Short Main Replacement of ~200' of a 2" Galvanized Pipe ahead of a DTM pavement project.
Waiting on 100% signatures - 5/19, Still waiting on DTM signatures 6/1/26
invitation to bid was sent out - 6/5. Due date is 6/22
Bid winner announced - Action pipe line, NOIA was sent, WAF created waiting on PO to send NTP and Construction permit. Contractor wants to start Aug. 1st
Pre con was done - Project in construction 8/4
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/27/2026 | TWPE 100% Design Plan Approval v.1 | REQUIRES RESUBMIT | |
| 05/11/2026 | TWPE 100% Design Plan Approval v.2 | APPROVED |