For conduit proofing we will use either a rodder or an air compressor depending on the length of the conduit run. The conduit is located within the Centurylink manhole system. Our contractor will lift the manhole lid to access the manhole and perform the required work. The contractor will be at each manhole for 30 minutes to an hour. Each run takes approximately 2-3 days. Houghton Rd Proofing_Drexel rd to Paseo Gran Escalera_Tucson - 2.5 miles Houghton Rd Proofing_Escalante Rd to Drexel_Tucson - 2 miles
Architects:
- DRC
- Wyyerd Fiber
- Wyyerd Fiber LLC
Contractors:
Plan Reviews
Plan Number - TR-FTTP-1126-00047
Plan Status: Needs Resubmittal
Plan Description: For conduit proofing we will use either a rodder or an air compressor depending on the length of the conduit run. The conduit is located within the Centurylink manhole system. Our contractor will lift the manhole lid to access the manhole and perform the required work. The contractor will be at each manhole for 30 minutes to an hour. Each run takes approximately 2-3 days.
Houghton Rd Proofing_Drexel rd to Paseo Gran Escalera_Tucson - 2.5 miles
Houghton Rd Proofing_Escalante Rd to Drexel_Tucson - 2 miles
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 11/19/2026 | Right of Way Review v.1 | REQUIRES RESUBMIT |