Plan: TR-FTTP-1026-00019
Plan Details
Apply Date:
10/28/2026
Applicant:
Max
Description:
Proofing on Valencia rd (Headley rd to Del Moral Blvd) = 3.5 miles - For conduit proofing we will use either a rodder or an air compressor depending on the length of the conduit run. The conduit is located within the Centurylink manhole system. Our contractor will lift the manhole lid to access the manhole and perform the required work. The contractor will be at each manhole for 30 minutes to an hour. Each run takes approximately 2-3 days.
Architects:
- Wyyerd Fiber
- Wyyerd Fiber LLC
Contractors:
Outstanding Plan Activity Conditions
Plan Number - TR-FTTP-1026-00019
Plan Description: Proofing on Valencia rd (Headley rd to Del Moral Blvd) = 3.5 miles - For conduit proofing we will use either a rodder or an air compressor depending on the length of the conduit run. The conduit is located within the Centurylink manhole system. Our contractor will lift the manhole lid to access the manhole and perform the required work. The contractor will be at each manhole for 30 minutes to an hour. Each run takes approximately 2-3 days.
| Date | Name | Approved | Comments |
|---|---|---|---|
| 11/05/2026 | sidewalk, pre activity | Not Approved | |
| 11/05/2026 | Traffic control set-up approved between 9AM - 3:30PM | Not Approved |
Plan Reviews
Plan Number - TR-FTTP-1026-00019
Plan Status: Approved
Plan Description: Proofing on Valencia rd (Headley rd to Del Moral Blvd) = 3.5 miles - For conduit proofing we will use either a rodder or an air compressor depending on the length of the conduit run. The conduit is located within the Centurylink manhole system. Our contractor will lift the manhole lid to access the manhole and perform the required work. The contractor will be at each manhole for 30 minutes to an hour. Each run takes approximately 2-3 days.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 10/28/2026 | Right of Way Review v.1 | APPROVED |