Plan: T22PI00011
Plan Details
Apply Date:
06/23/2022
Applicant:
Andie
Description:
La Escalera Residential Phase 1, Lots 1 - 219, Public Paving and Sewer Plans, SE of Valencia Rd & Harrison including unnamed new roads.
Architects:
- AMH
- BORDERLAND CONSTRUCTION
- Bowman
Contractors:
Outstanding Inspections
Permit Status:
Permit Number:
Permite Description:
Total Outstanding Inspections - 1
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/01/2024 | TRSP - PIA - Engineering Final - Completion of PIA Work (Final Lot Release/Acceptance) | Re-inspection required | Punch list has been uploaded and sent via email in order to address items needing replacement or repair. |
Completed Inspections
Permit Status:
Permit Number:
Permit Description:
Total Completed Inspections - 1
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/21/2025 | TRSP - PIA - Signage/Striping Final | Passed | Traffic Engineering Technician Victor Atondo approved 5/6/2025 letter sent |
Plan Reviews
Plan Number - T22PI00011
Plan Status: In Review
Plan Description: La Escalera Residential Phase 1, Lots 1 - 219, Public Paving and Sewer Plans, SE of Valencia Rd & Harrison including unnamed new roads.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 06/23/2022 | PIA - SUBMITTAL | 07/28/2022 | COMPLETED |
| 02/10/2023 | Private Improvement Agreement Review v.1 | REQUIRES RESUBMIT | |
| 07/31/2023 | Private Improvement Agreement Review v.1 | APPROVED | |
| 11/18/2022 | Private Improvement Agreement Review v.1 | REQUIRES RESUBMIT | |
| 03/13/2023 | Private Improvement Agreement Review v.2 | APPROVED | |
| 01/25/2024 | Private Improvement Agreement Review v.1 | APPROVED |