Inspection Status: Re-inspection required
Inspection History: TRSP - PIA - Engineering Final - Completion of PIA Work (Final Lot Release/Acceptance)
| Date |
Description |
Inspector |
Results |
Comments |
| 01/22/2025 |
TRSP - PIA - Engineering Final - Completion of PIA Work (Final Lot Release/Acceptance) |
|
Re-inspection required |
See attached PDF notes for reference of areas still in need of repair and/or replacement. |
| 05/06/2025 |
TRSP - PIA - Engineering Final - Completion of PIA Work (Final Lot Release/Acceptance) |
|
Passed |
Final approved punch list has been uploaded to documents. |
| 11/01/2024 |
TRSP - PIA - Engineering Final - Completion of PIA Work (Final Lot Release/Acceptance) |
|
Re-inspection required |
Punch list has been uploaded and sent via email in order to address items needing replacement or repair. |