Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Plan: T21PI00012
Plan Details
Apply Date:
09/08/2021
Applicant:
Unknown
Description:
Valencia Crossing Phase II, (Between Julian Wash and I-10) Paving Improvement for a portion of Greenway Wash Drive and Julian Wash Drive - includes new pavement, curb, sidewalk, ramps, and scuppers
Architects:
- Eagle Rock Excavating (ROC 169960)
- meritage homes
- Rick Engineering Company
- Rick Engineering Company, Inc.
- scott.kolt
Contractors:
Outstanding Inspections
Permit Status:
Permit Number:
Permite Description:
Total Outstanding Inspections - 2
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/21/2025 | TRSP - PIA - Engineering Final - Completion of PIA Work (Final Lot Release/Acceptance) | Re-inspection required | Three items need to be addressed and are outlined in attached final inspection report. | |
| 09/11/2025 | TRSP - PIA - Signage/Striping Final | Re-inspection required | Missing Blue RPM's at all fire hydrants: Ester Cruz Traffic Engineering Technician |
Completed Inspections
Permit Status:
Permit Number:
Permit Description:
Total Completed Inspections - 1
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/20/2023 | TRSP - PIA - Pre-Construction Meeting | Passed |
Plan Reviews
Plan Number - T21PI00012
Plan Status: Complete
Plan Description: Valencia Crossing Phase II, (Between Julian Wash and I-10) Paving Improvement for a portion of Greenway Wash Drive and Julian Wash Drive - includes new pavement, curb, sidewalk, ramps, and scuppers
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 09/08/2021 | PIA - SUBMITTAL | 10/27/2021 | COMPLETED |
| 12/16/2021 | PIA - SUBMITTAL | 12/16/2021 | COMPLETED |
| 12/12/2023 | Private Improvement Agreement Review v.1 | APPROVED |