Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Plan: S99-006
Plan Details
Apply Date:
02/22/1999
Applicant:
Unknown
Description:
REGALO DEL SOL
Architects:
- City of Tucson DTM Streets and Traffic Maintenance
- MW2 DEVELOPMENT INC
- Title Security Agency, LLC, a Delaware limited liability com. trust 202065-S as trustee, Ronda Tatro
Contractors:
Outstanding Inspections
Permit Status:
Permit Number:
Permite Description:
Total Outstanding Inspections - 2
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
01/26/2009 | TRSP - PIA - Engineering Final - Completion of PIA Work (Final Lot Release/Acceptance) | Re-inspection required | {Activity date: 01/26/2009; Status: Denied; Inspector: TSTOCKET; Comment: Entered by KMEDINA1 - SEE SIRE FOR PUNCH LIST} | |
06/25/2009 | COT - ENGR - Site - Assurance Release | Partial Pass | {Activity date: 06/25/2009; Status: Partial Approval; Inspector: DROBERTS; Comment: Entered by DROBERT2 - LOTS #5 AND #6 CAN BE RELEASED AT THIS TIME, THE REQUIRED DRIVEWAY REPAIRS HAVE BEEN COMPLETED AT THIS TIME.} ; {Activity date: 05/22/2009; Status: Denied; Inspector: DROBERTS; Comment: Entered by DROBERT2 - THE SITE WAS CHECKED FOR THE INITIAL RELEASE OF THE ASSURANCES AND HAS BEEN FOUND TO BE COMPLETE FOR THE INITIAL RELEASE. THE REQUESTED LOTS (5 & 6) CANNOT BE RELEASED AT THIS TIME UNTIL THE FOLLOWING ITEMS ARE ADDRESSED. THE SIDEWALKS FOR THE SITE HAVE BEEN POURED BUT HAVE BEEN POURED INCORRECTLY. BEFORE ANY OF THE LOTS (1 - 6) CAN BE APPROVED ALL DRIVEWAYS WILL HAVE TO BE RE-POURED. I WILL RE-INSPECT THIS SITE FOR THE RELEASE OF THESE LOTS ONCE THE DRIVE WAYS HAVE BEEN POURED CORRECTLY. ALL OTHER LOTS WILL BE RE-INSPECTED PRIOR TO APPROVING ADDITIONAL RELEASES. IF THERE ARE ANY QUESTIONS PLEASE FEEL FREE TO CONTACT DAVID ROBERTS AT 837-4992 AND 349-7643, LEAVE A MESSAGE IF I AM NOT IN OR AVAILABLE.} |
Completed Inspections
Permit Status:
Permit Number:
Permit Description:
Total Completed Inspections - 4
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/12/1999 | PDSD Site/Engineering Division - NPPO | Passed | {Activity date: 08/12/1999; Status: APPR; Inspector: JONEILL; Comment: Entered by JVOGELSB - APPROVED} ; {Activity date: 03/15/1999; Status: Correction Required; Inspector: JONEILL; Comment: Entered by JVOGELSB - CORRECTION REQUIRED} | |
12/03/1999 | PDSD Site/Engineering Division - Landscaping | Passed | {Activity date: 12/03/1999; Status: Approved; Inspector: JONEILL; Comment: Entered by LJACKSO1 - } ; {Activity date: 08/12/1999; Status: Correction Required; Inspector: JONEILL; Comment: Entered by JVOGELSB - CORRECTION REQUIRED} ; {Activity date: 08/12/1999; Status: Correction Required; Inspector: JONEILL; Comment: Entered by JVOGELSB - ADDTL COMMS - oneill: need 5 high wall n&e p.l.} | |
02/04/2009 | COT - WATR - Design Plan Construction | Passed | {Activity date: 02/04/2009; Status: Approved; Inspector: LHERNAND; Comment: Entered by KMEDINA1 - SEE SIRE FOR APPROVAL LETTER} | |
02/05/2009 | SPECIAL INSPECTION - OTHER (Third Party) | Passed | {Activity date: 02/05/2009; Status: Approved; Inspector: RMONTOYA; Comment: Entered by KMEDINA1 - SEE SIRE FOR APPROVAL LETTERS} |