Plan Number - S20-038
Plan Status: Approved
Plan Description: SILVERLAKE INDUSTR, Final Plat
Total Scheduled Inspections - 2
| Scheduled Date | Description | Inspector | Status |
|---|---|---|---|
| 11/04/2022 | TRSP - PIA - Engineering Final - Completion of PIA Work (Final Lot Release/Acceptance) | Scheduled | |
| 11/04/2022 | TRSP - PIA - Engineering Final - Completion of PIA Work (Final Lot Release/Acceptance) | Scheduled |
Outstanding Inspections
Permit Status:
Permit Number:
Permite Description:
Total Outstanding Inspections - 4
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/26/2022 | SPECIAL INSPECTION - Pima County Sewer (Third Party) | Not Ready | ||
| 10/26/2022 | COT - WATR - Design Plan Construction | Not Ready | ||
| 10/26/2022 | COT - ENGR - Site - Assurance Release | Not Ready | ||
| 10/26/2022 | TRSP - PIA - Engineering Final - Completion of PIA Work (Final Lot Release/Acceptance) | Scheduled |
Plan Reviews
Plan Number - S20-038
Plan Status: Approved
Plan Description: SILVERLAKE INDUSTR, Final Plat
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 06/03/2020 | SUBPLAT- OK TO SUBMIT | 06/05/2020 | COMPLETED |
| 06/05/2020 | MINOR SUBDIVISION REVIEW | 07/27/2020 | COMPLETED |
| 08/25/2020 | FINAL PLAT - PACKAGE | 08/27/2020 | COMPLETED |