Plan: S20-025
Plan Details
Apply Date:
04/15/2020
Applicant:
Gregory
Description:
LA ESTANCIA,PHASE2,PAR5,Final
Architects:
- DennisRoberts
- Sunbelt Holdings
Contractors:
Completed Inspections
Permit Status:
Permit Number:
Permit Description:
Total Completed Inspections - 3
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/11/2024 | TRSP - PIA - Engineering Partial - Added when Lot Releases Requested - Specify Lots | Passed | ||
07/18/2023 | COT - ENGR - Site - Assurance Release | Passed | Ok to release the following Lots 62-68, 73-79 inclusive | |
01/21/2025 | TRSP - PIA - Engineering Final - Completion of PIA Work (Final Lot Release/Acceptance) | Passed | Punchlist items completed 1-8-25 |
Plan Reviews
Plan Number - S20-025
Plan Status: Approved
Plan Description: LA ESTANCIA,PHASE2,PAR5,Final
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
03/13/2020 | SUBPLAT- OK TO SUBMIT | 04/16/2020 | COMPLETED |
04/16/2020 | FINAL PLAT - REVIEW | 05/19/2020 | COMPLETED |
04/19/2021 | ASSURANCES | 07/12/2021 | COMPLETED |
08/31/2020 | FINAL PLAT - REVIEW | 10/14/2020 | COMPLETED |
11/06/2020 | FINAL PLAT - PACKAGE | 11/13/2020 | COMPLETED |