Plan: S19-076
Plan Details
Apply Date:
10/29/2019
Applicant:
David
Description:
GEMATOS AGAPI LOTS, Final Plat
Architects:
- Good Boy Builders, LLC
Contractors:
Scheduled Inspections
Plan Number - S19-076
Plan Status: Approved
Plan Description: GEMATOS AGAPI LOTS, Final Plat
Total Scheduled Inspections - 2
| Scheduled Date | Description | Inspector | Status |
|---|---|---|---|
| 11/04/2022 | TRSP - PIA - Engineering Final - Completion of PIA Work (Final Lot Release/Acceptance) | Scheduled | |
| 11/04/2022 | TRSP - PIA - Engineering Final - Completion of PIA Work (Final Lot Release/Acceptance) | Scheduled |
Outstanding Inspections
Permit Status:
Permit Number:
Permite Description:
Total Outstanding Inspections - 4
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/26/2022 | SPECIAL INSPECTION - Pima County Sewer (Third Party) | Not Ready | ||
| 10/26/2022 | COT - WATR - Design Plan Construction | Not Ready | ||
| 10/26/2022 | COT - ENGR - Site - Assurance Release | Not Ready | ||
| 10/26/2022 | TRSP - PIA - Engineering Final - Completion of PIA Work (Final Lot Release/Acceptance) | Scheduled |
Plan Reviews
Plan Number - S19-076
Plan Status: Approved
Plan Description: GEMATOS AGAPI LOTS, Final Plat
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/14/2020 | MINOR SUBDIVISION REVIEW | 02/06/2020 | COMPLETED |
| 02/20/2020 | FINAL PLAT - PACKAGE | 03/23/2020 | COMPLETED |
| 09/30/2019 | SUBPLAT- OK TO SUBMIT | 10/30/2019 | COMPLETED |
| 10/30/2019 | MINOR SUBDIVISION REVIEW | 12/05/2019 | COMPLETED |