Plan: S18-094
Plan Details
Status:
Assurances
Type:
Land Division
Apply Date:
10/26/2018
Applicant:
Lisa
Description:
Mountain Enclave , Final Plat
Architects:
- KB Home
- Rick Engineering
- Sonoran Development Consulting
Contractors:
Scheduled Inspections
Plan Number - S18-094
Plan Status: Assurances
Plan Description: Mountain Enclave , Final Plat
Total Scheduled Inspections - 1
| Scheduled Date | Description | Inspector | Status |
|---|---|---|---|
| 04/04/2023 | COT - ENGR - Site - Assurance Release | Scheduled |
Completed Inspections
Permit Status:
Permit Number:
Permit Description:
Total Completed Inspections - 4
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/18/2023 | SPECIAL INSPECTION - Pima County Sewer (Third Party) | Passed | ||
| 04/18/2023 | COT - WATR - Design Plan Construction | Passed | ||
| 01/06/2022 | TRSP - PIA - Engineering Final - Completion of PIA Work (Final Lot Release/Acceptance) | Passed | PIA inspection approved by Inspection Staff. | |
| 04/18/2023 | COT - ENGR - Site - Assurance Release | Passed | FULL RELEASE OF ALL LOTS BUT NOT THE COMMON AREAS AT THIS TIME, CURRENT NECESSARY REPAIR WORK IS HAPPENING IN THE COMMON AREAS ON THE WEST SIDE OF THIS PROJECT. ONCE THIS WORK HAS BEEN COMPLETED THE DEVELOPER WILL BE NOTIFIED TO APPLY FOR THE RELEASE OF THE COMMON AREAS. |
Plan Reviews
Plan Number - S18-094
Plan Status: Assurances
Plan Description: Mountain Enclave , Final Plat
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/03/2021 | ASSURANCES | 08/03/2022 | COMPLETED |
| 10/03/2018 | SUBPLAT- OK TO SUBMIT | 11/01/2018 | COMPLETED |
| 11/01/2018 | FINAL PLAT - REVIEW | 12/07/2018 | COMPLETED |
| 11/08/2019 | FINAL PLAT - PACKAGE | 11/22/2019 | COMPLETED |