Plan: S16-018
Plan Details
Apply Date:
02/23/2016
Applicant:
Jeffrey
Description:
Carlton Circle Homes, Lots 1-8
Architects:
- Jas Engineering
Contractors:
Completed Inspections
Permit Status:
Permit Number:
Permit Description:
Total Completed Inspections - 4
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/11/2017 | COT - WATR - Design Plan Construction | Passed | {Activity date: 08/11/2017; Status: Approved; Inspector: AHINES; Comment: Entered by AHINES2 - PER TUCSON WATER FINAL INSPECTION AND ACCEPTANCE LETTER FROM 8/9/17} | |
| 11/28/2017 | SPECIAL INSPECTION - Pima County Sewer (Third Party) | Passed | {Activity date: 11/28/2017; Status: Approved; Inspector: KL; Comment: Entered by KLEE1 - Sewer acceptance letter in SIRE/ KL} | |
| 12/19/2017 | TRSP - PIA - Engineering Final - Completion of PIA Work (Final Lot Release/Acceptance) | Passed | {Activity date: 12/19/2017; Status: Approved; Inspector: Rleigh; Comment: Entered by RLEIGH1 - } | |
| 12/20/2017 | COT - ENGR - Site - Assurance Release | Passed | {Activity date: 12/20/2017; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } ; {Activity date: 08/07/2017; Status: Partial Approval; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } |
Plan Reviews
Plan Number - S16-018
Plan Status: Approved
Plan Description: Carlton Circle Homes, Lots 1-8
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/23/2016 | SUBPLAT- OK TO SUBMIT | 02/24/2016 | COMPLETED |
| 03/02/2016 | MINOR SUBDIVISION REVIEW | 04/27/2016 | COMPLETED |
| 04/27/2016 | MINOR SUBDIVISION REVIEW | 05/04/2016 | COMPLETED |
| 05/04/2016 | FINAL PLAT - PACKAGE | 05/06/2016 | COMPLETED |