Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Plan: S05-088
Plan Details
Apply Date:
05/26/2005
Applicant:
MMLA & PSOMAS INC
Description:
SUBC
Completed Inspections
Permit Status:
Permit Number:
Permit Description:
Total Completed Inspections - 8
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/20/2007 | ASSURANCE - PC WASTEWATER | SRAVAL | Approved | PHASE II LOTS 228-279, 378-472, 549-585 |
08/20/2007 | ASSURANCE - PC WASTEWATER | SRAVAL | Approved | PHASE I LOTS 534-548 |
08/20/2007 | ASSURANCE - UTILITY SERVICES | LHERNAND | Approved | PHASE I |
10/25/2007 | ASSURANCE - DSD | DROBERTS | Approved | THE SITE WAS CHECKED TO VERFIY WHAT WORK HAS BEEN COMPLETED SINCE THE PREVIOUS INSPECTION. THE FOLLOWING LOTS ARE EITHER UNDER CONSTRUCTION AT THIS TIME OR HAVE BEEN COMPLETED: 230-255, 295-300, 339-344, 348-350, 357-362, 399-400, 437-459, 549-585. THE INITIAL RELEASE OF 75% FOR THIS SITE HAS NOT BEEN REACHED AT THIS TIME. ADDITIONAL INSPECTIONS OF THE SITE WILL BE REQUIRED PRIOR TO THE FINAL RELEASE OF THE ASSURANCES. |
09/18/2008 | ASSURANCE - DOT TRAFFIC | TSTOCKET | Approved | PLAN NO. : I-2006-017 I inspected this PIA (Sierra Morado Unit #2- Phase 3) September 18, 2008 and found additional signs and posts need to be installed before this project is acceptable to Traffic Engineering; 1- Nine (9) "No Parking- Fire Access" signs and posts. 2- Three (3) "Dead End" / (3) "No Parking- Fire Access" (same posts) signs and posts. 3- Two (2) "No Parking Any Time w/ Arrows" signs and posts. |
09/19/2008 | ASSURANCE - DOT PERMITS & CODE | RLEIGH | Approved | PLAN NO. : I-2006-025 This office has inspected and found the Sierra Morado Unit 2, "Phase IV" improvements completed and in substantial conformance. The Engineeer-of-Record must submit the original "As Built" Mylars showing any revisions and/or changes to line and grade prior to acceptance by the City of Tucson for maintenance and operation. Additionally the Private Improvement Agreement (PIA) requires the owner/developer to pay any applicable fees for onsite roadway surface treatment (at a minimum fog coat). An offsite roadway surface treatment may be required depending on field conditions. Please submit fog coat fees of $21,721.33. The fees shall be paid to the City of Tucson, Department of Transportation (DOT). A letter of acceptance from the Engineering Division will follow after the receipt of the Mylars and applicable surface treatment fees have been paid. Please contact Traffic Engineering for any outstanding obligations pertaining to traffic signage and striping. |
09/19/2008 | ASSURANCE - DOT PERMITS & CODE | RLEIGH | Approved | PLAN NO. :I-2006-017 This office has inspected and found the Sierra Morado Unit 2, "Phase I" improvements completed and in substantial conformance. The Engineer-of-Record must submit the original "As Built" Mylars showing any revisions and/or changes to line and grade prior to acceptance by the City of Tucson for maintenance and operation. Additionally, the Private Improvement Agreement (PIA) requires the owner/developer to pay any applicable fees for onsite roadway surface treatment (at a minimum fog coat). An offsite roadway surface treatment may be required depending on field conditions. Please submit fog coat fees of $31,405.6. The fees shall be paid to the City of Tucson, Department of Transportation (DOT). A letter of acceptance from the Engineering Division will follow after the receipt of the Mylars and applicable surface treatment fees have been paid. Please contact Traffic Engineering for any outstanding obligations pertaining to traffic signage and striping. |
09/19/2008 | ASSURANCE - DOT PERMITS & CODE | RLEIGH | Approved | PLAN NO. : I-2006-017 This office has inspected and found the Sierra Morado Unit 2, Phase III improvements complpeted and in substantial conformance. The Engineer-of-Record must submit the original "As Built" Mylars showing any revisions and/or changes to line and grade prior to acceptance by the City of Tucson for maintenance and operation. Addditionally, the Private Improvement Agreement (PIA) requires the owner/ developer to pay any applicable fees for onsite roadway surface treatment (at a minimum fog coat). An offsite roadway surface treatment may be required depending on field conditions. Please submit fog coat fees of 22,501.85. The fees shall be paid to the City of Tucson, Department of Transportation (DOT). A letter of acceptance from the Engineering Division will follow after the receipt of the Mylars and applicable surface treatment fees have beeen paid. Please contact Traffic Engineering for any outstanding obligations pertaining to traffic signage and striping. |
Plan Reviews
Plan Number - S05-088
Plan Status: Final
Plan Description: SUBC
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/25/2006 | RESUBMITTAL - CDRC - FINAL PLAT REVIEW | 03/03/2006 | COMPLETED |
01/26/2006 | ASSURANCES | 02/28/2006 | COMPLETED |
02/01/2006 | RESUBMITTAL - CDRC - TENTATIVE PLAT REVIEW | 03/06/2006 | COMPLETED |
04/05/2006 | RESUBMITTAL - CDRC - FINAL PLAT REVIEW | 04/17/2006 | COMPLETED |
04/26/2006 | REVISION - TENTATIVE PLAT REVIEW | 06/03/2006 | COMPLETED |
05/19/2006 | FINAL PLAT PACKAGE | 06/16/2006 | COMPLETED |
06/01/2005 | TENTATIVE PLAT REVIEW | 07/19/2005 | COMPLETED |
08/05/2005 | RESUBMITTAL - CDRC - TENTATIVE PLAT REVIEW | 09/17/2005 | COMPLETED |
08/19/2005 | FINAL PLAT REVIEW | 11/01/2005 | COMPLETED |
10/28/2005 | RESUBMITTAL - CDRC - TENTATIVE PLAT REVIEW | 12/12/2005 | COMPLETED |
11/18/2005 | RESUBMITTAL - CDRC - FINAL PLAT REVIEW | 12/14/2005 | COMPLETED |
11/18/2005 | ASSURANCES | 12/15/2005 | COMPLETED |
12/23/2005 | RESUBMITTAL - CDRC - TENTATIVE PLAT REVIEW | 01/12/2006 | COMPLETED |
Completed Activity Conditions
Plan Number - S05-088
Plan Description: SUBC
Date | Name | Approved | Comments |
---|---|---|---|
CD | |||
CD |