Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Plan: S04-070
Plan Details
Apply Date:
06/25/2004
Applicant:
Shawn
Description:
CORONA ROAD ESTATES
Architects:
- City of Tucson DTM Streets and Traffic Maintenance
- FIDELITY NATIONAL TITLE AGENCY
- SOUTHERN ARIZONA LAND TRUST INC
Contractors:
Outstanding Inspections
Permit Status:
Permit Number:
Permite Description:
Total Outstanding Inspections - 1
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/11/2011 | COT - ENGR - Site - Assurance Release | Re-inspection required | {Activity date: 03/11/2011; Status: Continued; Inspector: DROBERTS; Comment: Entered by DROBERT5 - WAS CONTACTED BY KEITH DABURN/(520) 272-0219 AND DISCUSSED THE RELEASE OF LOT #10 FOR THIS SITE UNDER THE CURRENT SUBSTITUTE AGREEMENT, ALL OTHE LOTS WILL BE THROWN INTO ANOTHER SUBSTITUTE AGREEMENT NEXT WEEK. THIS WILL ALLOW FOR THE CONTRACTOR TO COVER UPTO 75% OF RELEASES BEFORE THEY WILL HAVE TO PLACE A CASH BOND.} ; {Activity date: 05/22/2008; Status: Partial Approval; Inspector: DROBERTS; Comment: Entered by DROBERT2 - OKAY FOR THE INITIAL RELEASE OF THE SITE.} |
Completed Inspections
Permit Status:
Permit Number:
Permit Description:
Total Completed Inspections - 2
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
02/26/2008 | TRSP – PIA - Engineering Final – Completion of PIA Work (Final Lot Release/Acceptance) | Passed | {Activity date: 02/26/2008; Status: Approved; Inspector: TSTOCKET; Comment: Entered by THAUSER1 - I-2005-043} | |
05/07/2008 | SPECIAL INSPECTION - Pima County Sewer (Third Party) | Passed | {Activity date: 05/07/2008; Status: Approved; Inspector: RMONTOYA; Comment: Entered by THAUSER1 - } |
Plan Reviews
Plan Number - S04-070
Plan Status: Approved
Plan Description: CORONA ROAD ESTATES
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
02/09/2006 | RESUBMITTAL - CDRC - FINAL PLAT REVIEW | 03/08/2006 | COMPLETED |
03/17/2005 | RESUBMITTAL - CDRC - TENTATIVE PLAT REVIEW | 04/27/2005 | COMPLETED |
04/05/2006 | FINAL PLAT PACKAGE | 04/18/2006 | COMPLETED |
05/02/2006 | FINAL PLAT PACKAGE | 05/10/2006 | COMPLETED |
05/26/2005 | RESUBMITTAL - CDRC - TENTATIVE PLAT REVIEW | 06/09/2005 | COMPLETED |
06/25/2004 | TENTATIVE PLAT REVIEW | 08/02/2004 | COMPLETED |
07/05/2005 | FINAL PLAT REVIEW | 08/13/2005 | COMPLETED |
12/19/2005 | RESUBMITTAL - CDRC - FINAL PLAT REVIEW | 01/25/2006 | COMPLETED |
12/20/2005 | ASSURANCES | 12/30/2005 | COMPLETED |