Permit: TW-CONS-0626-0080
Permit Details
Status:
Inspections
Type:
TW CIP Planning & Engineering
Address:
858 W LIMBERLOST DR
Address NEW:
858 W LIMBERLOST DR
Apply Date:
06/30/2026
Applicant:
Andres Amado
Description:
Opportunistic Short Main Replacement of ~200' of a 2" Galvanized Pipe ahead of a DTM pavement project. Waiting on 100% signatures - 5/19, Still waiting on DTM signatures 6/1/26 invitation to bid was sent out - 6/5. Due date is 6/22 Bid winner announced - Action pipe line, NOIA was sent, WAF created waiting on PO to send NTP and Construction permit. Contractor wants to start Aug. 1st
Outstanding Inspections
Permit Status: Inspections
Permit Number: TW-CONS-0626-0080
Permite Description: Opportunistic Short Main Replacement of ~200' of a 2" Galvanized Pipe ahead of a DTM pavement project.
Waiting on 100% signatures - 5/19, Still waiting on DTM signatures 6/1/26
invitation to bid was sent out - 6/5. Due date is 6/22
Bid winner announced - Action pipe line, NOIA was sent, WAF created waiting on PO to send NTP and Construction permit. Contractor wants to start Aug. 1st
Total Outstanding Inspections - 5
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/28/2026 | Used to track and report chlorination BacT testing and associated water loss. | N/A | In Field Accepted | |
| 09/10/2026 | Used to track and report system pressure testing and associated water loss. | N/A | In Field Accepted | |
| TWPE Pressure & Disinfection Testing | N/A | Scheduled | ||
| TWPE Daily Field Inspection | N/A | Scheduled | ||
| 08/21/2026 | TWPE Summary review of Daily Field Inspections | N/A | In Field Accepted |
Scheduled Inspections
Scheduled Inspections - TW-CONS-0626-0080
Status: Inspections
Description: Opportunistic Short Main Replacement of ~200' of a 2" Galvanized Pipe ahead of a DTM pavement project.
Waiting on 100% signatures - 5/19, Still waiting on DTM signatures 6/1/26
invitation to bid was sent out - 6/5. Due date is 6/22
Bid winner announced - Action pipe line, NOIA was sent, WAF created waiting on PO to send NTP and Construction permit. Contractor wants to start Aug. 1st
| Scheduled Date | Description | Entered By | Entered Date |
|---|---|---|---|
| 11/06/2026 | TWPE Daily Field Inspection | Scheduled | |
| 11/06/2026 | TWPE Summary review of Daily Field Inspections | Scheduled | |
| 09/22/2026 | TWPE Pressure & Disinfection Testing | Scheduled |