Permit: TR-UTL-1024-02004
Permit Details
Status:
Complete
Type:
Right-of-Way (ROW) - Utility
Address:
6200 S HEMISPHERE PL
Address NEW:
6200 S HEMISPHERE PL
Apply Date:
10/17/2024
Applicant:
Chelsey Bolinger
Description:
P.122870A (KAHNA) - BORE 4,372' & TRENCH 149’ TO PLACE CTL CONDUIT & FIBER CABLE. PLACE (1) FSAI CABINET, (18) HANDHOLES & (18) PEDESTALS.
Permit Reviews
Permit Number - TR-UTL-1024-02004
Permit Status: Complete
Permit Description: P.122870A (KAHNA) - BORE 4,372' & TRENCH 149’ TO PLACE CTL CONDUIT & FIBER CABLE. PLACE (1) FSAI CABINET, (18) HANDHOLES & (18) PEDESTALS.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 10/18/2024 | RIGHT-OF-WAY REVIEW v.1 | 10/22/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-UTL-1024-02004
Permit Status: Complete
Permit Description: P.122870A (KAHNA) - BORE 4,372' & TRENCH 149’ TO PLACE CTL CONDUIT & FIBER CABLE. PLACE (1) FSAI CABINET, (18) HANDHOLES & (18) PEDESTALS.
Total Outstanding Activity Conditions - 3
| Date | Name |
|---|---|
| 10/21/2024 | Traffic Control set-up approved between 7AM - 5PM |
| 10/21/2024 | Other Permits/Projects are or will be active in your project area. Please coordinate with the project manager in charge of any existing traffic control set-ups in your project area. |
| 10/21/2024 | Pavement Patch type Shall Be in conformance to the current edition of the City of Tucson Public Utility Administrative Manual. |
Completed Inspections
Permit Status: Complete
Permit Number: TR-UTL-1024-02004
Permit Description: P.122870A (KAHNA) - BORE 4,372' & TRENCH 149’ TO PLACE CTL CONDUIT & FIBER CABLE. PLACE (1) FSAI CABINET, (18) HANDHOLES & (18) PEDESTALS.
Total Completed Inspections - 5
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/13/2025 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | on-site meeting with Chris from Pauley and bore crew, AWP setting up traffic control today, beginning potholing around FSA1 | |
| 04/10/2025 | TRSP - ROW - Backfill - Placement/Compaction | Passed | Work is already complete and final pavement patch is already in place. | |
| 05/05/2025 | TRSP - ROW - Barricade - Setup/Routine | Passed | Work is complete | |
| 05/05/2025 | TRSP - ROW - Barricade Takedown | Passed | Work is complete and all traffic control has been removed from the job site | |
| 05/05/2025 | TRSP - ROW - Final | Passed | Work is complete |