Permit: TR-UTL-1024-01961
Permit Details
Status:
Complete
Type:
Right-of-Way (ROW) - Utility
Address:
8800 E SPEEDWAY BL
Address NEW:
8800 E SPEEDWAY BL
Apply Date:
10/11/2024
Applicant:
Description:
Lowering TEP conduits at property to avoid conflict with water and sewer install at the property.
Permit Reviews
Permit Number - TR-UTL-1024-01961
Permit Status: Complete
Permit Description: Lowering TEP conduits at property to avoid conflict with water and sewer install at the property.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 10/11/2024 | RIGHT-OF-WAY REVIEW v.1 | 10/14/2024 | REQUIRES RESUBMIT |
| 10/16/2024 | RIGHT-OF-WAY REVIEW v.2 | 10/17/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-UTL-1024-01961
Permit Status: Complete
Permit Description: Lowering TEP conduits at property to avoid conflict with water and sewer install at the property.
Total Outstanding Activity Conditions - 3
| Date | Name |
|---|---|
| 10/11/2024 | PRE-CON |
| 10/17/2024 | Traffic Control Condition. |
| 10/17/2024 | Traffic control set-up approved between 9AM - 3:30PM |
Outstanding Inspections
Permit Status: Complete
Permit Number: TR-UTL-1024-01961
Permite Description: Lowering TEP conduits at property to avoid conflict with water and sewer install at the property.
Total Outstanding Inspections - 2
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/17/2024 | TRSP - ROW - Backfill - Placement/Compaction | N/A | Re-inspection required | |
| 12/17/2024 | TRSP - ROW - Final | N/A | Re-inspection required |
Completed Inspections
Permit Status: Complete
Permit Number: TR-UTL-1024-01961
Permit Description: Lowering TEP conduits at property to avoid conflict with water and sewer install at the property.
Total Completed Inspections - 3
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/19/2024 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | ||
| 05/28/2025 | TRSP - ROW - Backfill - Placement/Compaction | Passed | ||
| 05/28/2025 | TRSP - ROW - Final | Passed |