Permit: TR-UTL-0726-01127
Permit Details
Status:
Inspections
Type:
Right-of-Way (ROW) - Utility
Address:
9401 E 22ND ST
Address NEW:
9401 E 22ND ST
Apply Date:
07/08/2026
Applicant:
Aridai Rosas
Description:
Franchise project - Approx. 5,550' of boring under pavement and dirt with an approximate 1,110' trench in dirt/pavement. Crews working across 22nd Street with lane closures.
Permit Reviews
Permit Number - TR-UTL-0726-01127
Permit Status: Inspections
Permit Description: Franchise project - Approx. 5,550' of boring under pavement and dirt with an approximate 1,110' trench in dirt/pavement. Crews working across 22nd Street with lane closures.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/05/2026 | RIGHT-OF-WAY REVIEW v.3 | 08/07/2026 | REQUIRES RESUBMIT |
| 07/09/2026 | RIGHT-OF-WAY REVIEW v.1 | 07/20/2026 | REQUIRES RESUBMIT |
| 08/11/2026 | RIGHT-OF-WAY REVIEW v.4 | 08/12/2026 | APPROVED |
| 07/28/2026 | RIGHT-OF-WAY REVIEW v.2 | 08/04/2026 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TR-UTL-0726-01127
Permit Status: Inspections
Permit Description: Franchise project - Approx. 5,550' of boring under pavement and dirt with an approximate 1,110' trench in dirt/pavement. Crews working across 22nd Street with lane closures.
Total Outstanding Activity Conditions - 11
| Date | Name |
|---|---|
| 07/14/2026 | BUS STOP IN THE AREA, CONTACT SUN TRAN DISPATCH, AT 520-206-8934 AT LEAST 48-BUSINESS HOURS PRIOR TO START OF WORK FOR COORDINATION. |
| 07/14/2026 | Traffic control set-up approved between 9AM - 3:30PM |
| 07/14/2026 | Other Permits/Projects are or will be active in your project area. Please coordinate with the project manager in charge of any existing traffic control set-ups in your project area. |
| 07/14/2026 | UNDER A PAVEMENT MORATORIUM, ANY NEW ASPHALT THAT IS DISTURBED WILL REQUIRE A 2” MILL AND OVERLAY FOR 25’ IN EACH DIRECTION FROM THE OUTSIDE OF THE CUT FOR ALL EFFECTED TRAVEL LANES. |
| 07/14/2026 | Pre- activity/construction meeting with City inspectors to be held 72 hours in advance of work start. Please request Inspections in your permit portal on TDC Online. |
| 07/14/2026 | PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING. |
| 08/12/2026 | Bike Lane Access and Accommodation 1) Posted Speeds 30 Mph or Less – Less than 14 lane - Use of the R4-11 alone is acceptable and preferred over Share The Road sign - 2) Posted Speeds 30 Mph or less – greater than 14 lane - Use of Share The Road sign is preferred 3) Posted Speeds 30 Mph or More – Any Lane Size - Provide a reasonable alternative for cyclists, such as a paved path, space behind barricades, or bike detour. Acceptable to direct cyclists to the sidewalk when properly signed depending on conditions 4) Bike lane to be maintained within Traffic Control closure and Share may Pedestrian detour path with proper R9-6 Sign. |
| 08/12/2026 | The following extended traffic control set-up times were approved: Approved for 24hr TC Setup in plan designated areas |
| 08/12/2026 | Message Boards to be Placeds 5 days in advance of Start of Work and remain Through Project.. |
| 08/12/2026 | Pedestrian Access & Sidewalk PEDESTRIAN ACCESS MUST BE PROVIDED AND MAINTIANED PER MUTCD CHAPTER 6D. FIELD ADJUSTMENTS MAY BE REQUIRED. REPLACE/REPAIR SIDEWALK PANELS PER PAG STANDARD DETAIL 200\206 . PEDESTRIAN DETOUR ROUTE ON SAME SIDE OF RIGHT OF WAY TO BE PROVIDED. PER CITY CODE AND POLICY. Refer to MUTCD Chapter 6 Figure 6P-28, and 6K figure 6K-2. Refer to COT Utility manual Page 41 - 42 Refer to COT 2015 Addition to the MUTCD section 14 |
| 08/12/2026 | Traffic Control Plans to be set per Approved plans, including on plan Red Line field comments |
Outstanding Inspections
Permit Status: Inspections
Permit Number: TR-UTL-0726-01127
Permite Description: Franchise project - Approx. 5,550' of boring under pavement and dirt with an approximate 1,110' trench in dirt/pavement. Crews working across 22nd Street with lane closures.
Total Outstanding Inspections - 1
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | N/A | Scheduled |
Scheduled Inspections
Scheduled Inspections - TR-UTL-0726-01127
Status: Inspections
Description: Franchise project - Approx. 5,550' of boring under pavement and dirt with an approximate 1,110' trench in dirt/pavement. Crews working across 22nd Street with lane closures.
| Scheduled Date | Description | Entered By | Entered Date |
|---|---|---|---|
| 08/19/2026 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Scheduled |