Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Details

Status:
Needs Resubmittal
Type:
Right-of-Way (ROW) - Utility
Address NEW:
4000 N SILVERBELL RD
Apply Date:
07/07/2026
Applicant:
Garcia David
Description:
MMR Fiber-- SEGMENT 2 (Plan Phase 2) - THIS JOB PLACES 4600' OF (2)2" AND (4)7-WAY HDPE CONDUITS ALONG N SILVERBELL RD. METHOD OF CONSTRUCTION TO BE DIRECTIONAL BORING AND/OR DIGGING/TRENCHING DEPENDING ON AREA AND ENGINEERING DRAWINGS. POSSIBLE PITS AND PLACING HANDHOLES. FIBER CABLE TO BE PLACED IN CONDUIT LOOPING INTO HANDHOLE. (DTM Note-- Refer to Attachments for Related Permit from Contractor)

Permit Reviews

Permit Number - TR-UTL-0726-01115
Permit Status: Needs resubmittal
Permit Description: MMR Fiber-- SEGMENT 2 (Plan Phase 2) - THIS JOB PLACES 4600' OF (2)2" AND (4)7-WAY HDPE CONDUITS ALONG N SILVERBELL RD. METHOD OF CONSTRUCTION TO BE DIRECTIONAL BORING AND/OR DIGGING/TRENCHING DEPENDING ON AREA AND ENGINEERING DRAWINGS. POSSIBLE PITS AND PLACING HANDHOLES. FIBER CABLE TO BE PLACED IN CONDUIT LOOPING INTO HANDHOLE. (DTM Note-- Refer to Attachments for Related Permit from Contractor)
Start Date Submittal Complete Date Status  
07/09/2026 RIGHT-OF-WAY REVIEW v.2 N/A REQUIRES RESUBMIT Review Details
07/08/2026 RIGHT-OF-WAY REVIEW v.1 N/A REQUIRES RESUBMIT Review Details
07/17/2026 RIGHT-OF-WAY REVIEW v.1 07/20/2026 REQUIRES RESUBMIT Review Details