Permit: TR-UTL-0326-00465
Permit Details
Status:
Issued
Type:
Right-of-Way (ROW) - Utility
Address:
1815 W SAINT MARYS RD
Address NEW:
1815 W SAINT MARYS RD
Apply Date:
03/06/2026
Applicant:
Esteban Vega - Desert Barricades
Description:
WO T155282 (ST MARYS) - reconductor 3 spans of overhead, replace 4 wood poles with steel poles, replace 2 anchors, remove 1 anchor, replace 3 – 4” risers, install 5 new poles and 5 new spans of overhead, install 1 – 6” riser & WO T173264 (CAMINO SANTIAGO) - Install 1 – PME9, 1 – PME11, 2 – 6” risers, 2,140’ of cable 06/15/2026 - Request for 90 Day Renewal as of 06/23/2026
Permit Reviews
Permit Number - TR-UTL-0326-00465
Permit Status: Issued
Permit Description: WO T155282 (ST MARYS) - reconductor 3 spans of overhead, replace 4 wood poles with steel poles, replace 2 anchors, remove 1 anchor, replace 3 – 4” risers, install 5 new poles and 5 new spans of overhead, install 1 – 6” riser & WO T173264 (CAMINO SANTIAGO) - Install 1 – PME9, 1 – PME11, 2 – 6” risers, 2,140’ of cable
06/15/2026 - Request for 90 Day Renewal as of 06/23/2026
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/11/2026 | RIGHT-OF-WAY REVIEW v.2 | 03/13/2026 | REQUIRES RESUBMIT |
| 03/18/2026 | RIGHT-OF-WAY REVIEW v.3 | 03/23/2026 | APPROVED |
| 03/06/2026 | RIGHT-OF-WAY REVIEW v.1 | 03/10/2026 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TR-UTL-0326-00465
Permit Status: Issued
Permit Description: WO T155282 (ST MARYS) - reconductor 3 spans of overhead, replace 4 wood poles with steel poles, replace 2 anchors, remove 1 anchor, replace 3 – 4” risers, install 5 new poles and 5 new spans of overhead, install 1 – 6” riser & WO T173264 (CAMINO SANTIAGO) - Install 1 – PME9, 1 – PME11, 2 – 6” risers, 2,140’ of cable
06/15/2026 - Request for 90 Day Renewal as of 06/23/2026
Total Outstanding Activity Conditions - 5
| Date | Name |
|---|---|
| 03/09/2026 | This project is located in an Archaeological Sensitivity Zone. An Archaeological Monitor hired by the permit applicant is required to be on-site during any digging, unless a waiver is issued. Monitoring reports are to be submitted to Historic Preservation Office, City of Tucson, P.O. Box 27210, Tucson, AZ 85726.** Please contact Historic Preservation Office at PDSDHistoric@tucsonaz.gov |
| 03/09/2026 | Bus stop in the area, contact Joe Garcia, Sun Tran Dispatch, at 520-576-8726 at least 48-business hours prior to start of work for coordination. |
| 03/09/2026 | Traffic control set-up approved between 9AM - 3:30PM |
| 03/19/2026 | Bike Lane Access and Accommodation 1) Posted Speeds 30 Mph or Less – Less than 14 lane - Use of the R4-11 alone is acceptable and preferred over Share The Road sign - 2) Posted Speeds 30 Mph or less – greater than 14 lane - Use of Share The Road sign is preferred 3) Posted Speeds 30 Mph or More – Any Lane Size - Provide a reasonable alternative for cyclists, such as a paved path, space behind barricades, or bike detour. Acceptable to direct cyclists to the sidewalk when properly signed depending on conditions 4) Bike lane to be maintained within Traffic Control closure and Share may Pedestrian detour path with proper R9-6 Sign. |
| 03/19/2026 | Pre-Activity Meeting w/Inspections Pre- activity/construction meeting with City inspectors to be held 72 hours in advance of work start. Please request Inspections in your permit portal on TDC Online. PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING. |
Completed Inspections
Permit Status: Issued
Permit Number: TR-UTL-0326-00465
Permit Description: WO T155282 (ST MARYS) - reconductor 3 spans of overhead, replace 4 wood poles with steel poles, replace 2 anchors, remove 1 anchor, replace 3 – 4” risers, install 5 new poles and 5 new spans of overhead, install 1 – 6” riser & WO T173264 (CAMINO SANTIAGO) - Install 1 – PME9, 1 – PME11, 2 – 6” risers, 2,140’ of cable
06/15/2026 - Request for 90 Day Renewal as of 06/23/2026
Total Completed Inspections - 3
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/06/2026 | TRSP - ROW - Barricade - Setup/Routine | Passed | ||
| 05/01/2026 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | ||
| 06/04/2026 | TRSP - ROW - Backfill - Placement/Compaction | Passed | The backfill for TEP has been completed by Tricon permit will remain open until TEP is completed with all their overhead and their pole sets for this job |