Permit: TR-ROW-1124-01314
Permit Details
Apply Date:
11/07/2024
Applicant:
Description:
Trench 35’L X2’W X4’D/ 25’ in asphalt. To install the water line. Work hours 5pm -5am.*** Related permit #TR-ROW-1024-01280
Permit Reviews
Permit Number - TR-ROW-1124-01314
Permit Status: Complete
Permit Description: Trench 35’L X2’W X4’D/ 25’ in asphalt. To install the water line. Work hours 5pm -5am.***
Related permit #TR-ROW-1024-01280
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 11/08/2024 | RIGHT-OF-WAY REVIEW v.1 | 11/08/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-ROW-1124-01314
Permit Status: Complete
Permit Description: Trench 35’L X2’W X4’D/ 25’ in asphalt. To install the water line. Work hours 5pm -5am.***
Related permit #TR-ROW-1024-01280
Total Outstanding Activity Conditions - 3
| Date | Name |
|---|---|
| 11/08/2024 | The following extended traffic control set-up times were approved: |
| 11/08/2024 | PRE-CON/PAVEMENT/SIDEWALK |
| 11/08/2024 | TNE required for overnight work |
Completed Inspections
Permit Status: Complete
Permit Number: TR-ROW-1124-01314
Permit Description: Trench 35’L X2’W X4’D/ 25’ in asphalt. To install the water line. Work hours 5pm -5am.***
Related permit #TR-ROW-1024-01280
Total Completed Inspections - 4
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/27/2025 | TRSP - ROW - Barricade - Setup/Routine | Passed | ||
| 01/13/2025 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | ||
| 01/27/2025 | TRSP - ROW - Backfill - Placement/Compaction | Passed | ||
| 01/27/2025 | TRSP - ROW - Final | Passed |