Permit Details

Status:
Complete
Type:
Right-of-Way (ROW)
Address:
339 S STONE AV
Apply Date:
11/09/2022
Applicant:
Ricardo Yanez
Description:
Bore 32 ft, trench asphalt 32 ft, place 2 " pvc conduit for Zayo fiber

Permit Reviews

Permit Number - TR-ROW-1122-00054
Permit Status: Complete
Permit Description: Bore 32 ft, trench asphalt 32 ft, place 2 " pvc conduit for Zayo fiber
Start Date Submittal Complete Date Status  
11/30/2022 RIGHT-OF-WAY REVIEW v.1 11/30/2022 APPROVED Review Details

Conditions

Permit Number - TR-ROW-1122-00054
Permit Status: Complete
Permit Description: Bore 32 ft, trench asphalt 32 ft, place 2 " pvc conduit for Zayo fiber
Date Description Comments
11/30/2022 Emergency – After the fact permit
11/30/2022 Traffic control set-up approved between 9AM - 3:30PM
11/30/2022 Other Permits/Projects are or will be active in your project area. Please coordinate with the project manager in charge of any existing traffic control set-ups in your project area.

Outstanding Inspections

Permit Status: Complete
Permit Number: TR-ROW-1122-00054
Permite Description: Bore 32 ft, trench asphalt 32 ft, place 2 " pvc conduit for Zayo fiber
Total Outstanding Inspections - 3
Last Inspection Date Description Inspector Results Comments
01/05/2023 TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting N/A Complete (Recurring) Original preconstruction meeting was held on December 16, 2022
02/10/2023 TRSP - ROW - SITE INSPECTION N/A Complete (Recurring) Work will resume after the gem show.
01/30/2023 TRSP - ROW - Recurring N/A Complete (Recurring) Work is on hold until after the gem show.

Completed Inspections

Permit Status: Complete
Permit Number: TR-ROW-1122-00054
Permit Description: Bore 32 ft, trench asphalt 32 ft, place 2 " pvc conduit for Zayo fiber
Total Completed Inspections - 1
Date Description Inspector Results Comments
03/09/2023 TRSP - ROW - Final/Close-Out Passed All underground work is complete. Permanent asphalt patches are in place. No further issues.

Documents

File Name Document Type  
COT - TR - ROW PERMIT.PDF DOCUMENTS VIEW