Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Details

Status:
Complete
Type:
Right-of-Way (ROW)
Address:
7975 E STELLA RD
Address NEW:
7975 E STELLA RD
Apply Date:
10/16/2024
Applicant:
Description:
Installation of UGC pathways for the fiber connection of Kolb C Water Reservoir. Security Upgrade Project.

Permit Reviews

Permit Number - TR-ROW-1024-01222
Permit Status: Complete
Permit Description: Installation of UGC pathways for the fiber connection of Kolb C Water Reservoir. Security Upgrade Project.
Start Date Submittal Complete Date Status  
10/31/2024 RIGHT-OF-WAY REVIEW v.3 11/01/2024 APPROVED Review Details
10/28/2024 RIGHT-OF-WAY REVIEW v.2 10/28/2024 REQUIRES RESUBMIT Review Details
10/16/2024 RIGHT-OF-WAY REVIEW v.1 10/18/2024 REQUIRES RESUBMIT Review Details

Outstanding Activity Conditions

Permit Number - TR-ROW-1024-01222
Permit Status: Complete
Permit Description: Installation of UGC pathways for the fiber connection of Kolb C Water Reservoir. Security Upgrade Project.
Total Outstanding Activity Conditions - 3
Date Name
10/17/2024 Traffic control set-up approved between 9AM - 3:30PM
10/17/2024 Other Permits/Projects are or will be active in your project area. Please coordinate with the project manager in charge of any existing traffic control set-ups in your project area.
10/17/2024 BUS STOP IN THE AREA, CONTACT SUN TRAN DISPATCH, AT 520-206-8934 AT LEAST 48-BUSINESS HOURS PRIOR TO START OF WORK FOR COORDINATION.

Completed Inspections

Permit Status: Complete
Permit Number: TR-ROW-1024-01222
Permit Description: Installation of UGC pathways for the fiber connection of Kolb C Water Reservoir. Security Upgrade Project.
Total Completed Inspections - 4
Date Description Inspector Results Comments
11/13/2024 TRSP - ROW - Barricade - Setup/Routine Passed Snow fencing, barricades, and early warning signs in place for job site
11/13/2024 TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting Passed Pre-con meeting held with Sturgeon on 11/8
02/05/2025 TRSP - ROW - Barricade Takedown Passed all traffic control has been removed from the job site and the area is clean
02/05/2025 TRSP - ROW - Final Passed