Permit: TR-ROW-0925-01109
Permit Details
Apply Date:
09/09/2025
Applicant:
ANGEL MORALES
Description:
Please submit. Install 2 standard driveways (SD 206) and 35’ of standard sidewalk (SD 200) and ramps***
Permit Reviews
Permit Number - TR-ROW-0925-01109
Permit Status: Inspections
Permit Description: Please submit. Install 2 standard driveways (SD 206) and 35’ of standard sidewalk (SD 200) and ramps***
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 09/10/2025 | RIGHT-OF-WAY REVIEW v.1 | 09/14/2025 | APPROVED |
Outstanding Activity Conditions
Permit Number - TR-ROW-0925-01109
Permit Status: Inspections
Permit Description: Please submit. Install 2 standard driveways (SD 206) and 35’ of standard sidewalk (SD 200) and ramps***
Total Outstanding Activity Conditions - 7
| Date | Name |
|---|---|
| 09/10/2025 | PRE-CON/PAVEMENT/SIDEWALK |
| 09/10/2025 | Traffic control set-up approved between 9AM - 3:30PM |
| 09/12/2025 | The following extended traffic control set-up times were approved: 24 hr. Closure for Pedestrian detour. |
| 09/12/2025 | Bike Lane Access and Accommodation |
| 09/12/2025 | Bus Stop & Route |
| 09/12/2025 | Pedestrian Detour Route |
| 09/12/2025 | Private Property |
Outstanding Inspections
Permit Status: Inspections
Permit Number: TR-ROW-0925-01109
Permite Description: Please submit. Install 2 standard driveways (SD 206) and 35’ of standard sidewalk (SD 200) and ramps***
Total Outstanding Inspections - 2
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/03/2025 | TRSP - ROW - Concrete - Subgrade/Forms (Pre-Pour) | N/A | Deferred | |
| 11/05/2025 | TRSP - ROW - Backfill - Placement/Compaction | N/A | Deferred |
Completed Inspections
Permit Status: Inspections
Permit Number: TR-ROW-0925-01109
Permit Description: Please submit. Install 2 standard driveways (SD 206) and 35’ of standard sidewalk (SD 200) and ramps***
Total Completed Inspections - 6
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/19/2025 | TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting | Passed | ||
| 09/26/2025 | TRSP - ROW - Barricade - Setup/Routine | Passed | ||
| 10/06/2025 | TRSP - ROW - Concrete - Subgrade/Forms (Pre-Pour) | Passed | ||
| 11/05/2025 | TRSP - ROW - Concrete - Acceptance (Post-Pour) | Passed | ||
| 02/25/2026 | TRSP - ROW - Final | Passed | ||
| 02/25/2026 | TRSP - ROW - Barricade Takedown | Passed |